Project Schedule
Construction activities started in late August 2007 and are scheduled to be completed in December 2009.
 |
By clicking on the thumbnail image on the left, users can view the Department's high level project schedule.
Activities to the left of the data date (blue vertical line) have been completed. Activities to the right of the data date are pending.
|
Two Week Look Ahead:
The following construction activities have been scheduled for the next two weeks (11/2/2009 to 11/14/2009) as part of the Stage 3 and 4 construction:
-
Seismic retrofitting of the Castaic Creek Bridge across the Interstate 5 freeway.
-
Install metal beam guard rail on the east side of The Old Road.
-
Construct walls for Cast-In-Drilled-Hole concrete piles.
-
Drill holes for the Cast-In-Drill-Hole concrete piles.
|