Project Schedule
Construction activities started in late August 2007 and are scheduled to be completed in June 2009.
 |
By clicking on the thumbnail image on the left, users can view the Department's high level project schedule.
Activies to the left of the data date (blue vertical line) have been completed. Activites to the right of the data date are pending.
|
Two Week Look Ahead:
The following construction activities have been scheduled for the next two weeks (10/03/2008 to 10/17/2008) as part of the Stage 1 and 2 construction:
-
Install shoring for Castaic Creek Bridge piers
-
Grading and paving northwest portion of Hasley Canyon and The Old Road and also, east side of The Old Road.
-
Dewatering operation in Castaic Creek.
-
Construction of northern portion of the new Hasley Canyon Bridge.
|