Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.06.001 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) |
0.10
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $5,000.00 | $5,000.00 |
001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.07
| 7 | MTH | $500.00 | $500.00 |
$3,500.00
| $500.00 | $500.00 |
001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) |
0.04
| 1 | LS | $2,000.00 | $2,000.00 |
$2,000.00
| $2,000.00 | $2,000.00 |
001.07.004 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) |
0.10
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $5,000.00 | $5,000.00 |
001.07.007 | IMPLEMENTATION OF THE SWPPP |
0.51
| 1 | LS | $15,000.00 | $25,000.00 |
$25,000.00
| $40,640.00 | $35,000.00 |
001.08.003 | OFFICE FACILITIES |
0.37
| 1 | LS | $28,000.00 | $18,500.00 |
$18,500.00
| $25,500.00 | $18,500.00 |
001.09.003 | MOBILIZATION |
5.67
| 1 | LS | $110,000.00 | $280,000.00 |
$280,000.00
| $292,040.00 | $280,000.00 |
300.01.065 | CONCRETE REMOVAL (NON-REINFORCED) |
0.18
| 40 | CY | $250.00 | $220.00 |
$8,800.00
| $292.60 | $328.00 |
300.02.003 | UNCLASSIFIED EXCAVATION |
0.34
| 195 | CY | $70.00 | $86.00 |
$16,770.00
| $171.80 | $160.00 |
300.05.002 | IMPORTED BORROW |
0.28
| 215 | CY | $120.00 | $65.00 |
$13,975.00
| $176.00 | $164.00 |
301.02.005 | CRUSHED MISCELLANEOUS BASE |
0.33
| 137 | CY | $120.00 | $120.00 |
$16,440.00
| $225.60 | $255.00 |
302.01.007 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") |
2.81
| 266988 | SF | $0.20 | $0.52 |
$138,833.76
| $0.55 | $0.52 |
302.05.013 | AC PAVEMENT |
0.08
| 17 | TON | $175.00 | $230.00 |
$3,910.00
| $287.40 | $250.00 |
302.05.016 | AC PAVEMENT(DRIVEWAYS) |
0.43
| 94 | TON | $120.00 | $225.00 |
$21,150.00
| $245.60 | $230.00 |
302.05.019 | AC PAVEMENT(LEVELING COURSE) |
5.33
| 3295 | TON | $90.00 | $80.00 |
$263,600.00
| $93.80 | $95.00 |
302.09.003 | ASPHALT RUBBER HOT MIX |
27.98
| 11921 | TON | $100.00 | $116.00 |
$1,382,836.00
| $113.40 | $116.00 |
302.09.005 | ASPHALT RUBBER HOT MIX (TEST STRIP) |
1.37
| 500 | TON | $115.00 | $135.00 |
$67,500.00
| $139.00 | $143.00 |
302.15.003 | CIR AC PAVEMENT, 4" THICK |
28.28
| 146323 | SY | $7.00 | $9.55 |
$1,397,384.65
| $10.07 | $10.00 |
302.15.007 | EMULSIFIED RECYCLING AGENT |
10.67
| 824 | TON | $700.00 | $640.00 |
$527,360.00
| $632.80 | $625.00 |
303.01.033 | CONCRETE BARRIER (TYPE 60) |
0.41
| 64 | LF | $150.00 | $315.00 |
$20,160.00
| $325.00 | $345.00 |
303.01.370 | HEADWALL (CALTRANS STD PLAN D89) |
0.10
| 4 | CY | $1,500.00 | $1,180.00 |
$4,720.00
| $6,022.00 | $4,530.00 |
303.05.045 | PCC DRIVEWAYS, 4" THICK |
0.46
| 3133 | SF | $9.00 | $7.25 |
$22,714.25
| $9.25 | $8.00 |
306.01.119 | 30" CSP, 14 GAGE |
0.11
| 5 | LF | $250.00 | $1,100.00 |
$5,500.00
| $473.40 | $277.00 |
306.01.119 | 24" CSP, 14 GAGE |
0.04
| 2 | LF | $200.00 | $1,000.00 |
$2,000.00
| $487.20 | $340.00 |
310.05.014 | DETAIL 38A (THERMOPLASTIC) |
0.02
| 360 | LF | $3.50 | $2.15 |
$774.00
| $2.41 | $2.15 |
310.05.022 | DETAIL 27B (THERMOPLASTIC) |
0.86
| 98400 | LF | $1.50 | $0.43 |
$42,312.00
| $0.41 | $0.43 |
310.05.034 | PAVEMENT MARKINGS (THERMOPLASTIC) |
0.05
| 357 | SF | $6.00 | $6.40 |
$2,284.80
| $7.40 | $6.40 |
310.05.040 | 12" STRIPING (THERMOPLASTIC) |
0.01
| 164 | LF | $3.50 | $4.30 |
$705.20
| $3.70 | $4.00 |
315.06.003 | SIGN PANEL |
0.28
| 124 | EA | $150.00 | $112.00 |
$13,888.00
| $110.20 | $109.00 |
315.06.005 | FURNISH ONE-POST (ROADSIDE SIGN) |
0.18
| 107 | EA | $150.00 | $85.00 |
$9,095.00
| $77.60 | $80.00 |
315.06.015 | INSTALL ONE-POST (ROADSIDE SIGN) |
0.37
| 107 | EA | $150.00 | $171.00 |
$18,297.00
| $101.70 | $65.00 |
315.06.017 | INSTALL SIGN (STRAP AND SADDLE BRACKET) |
0.23
| 124 | EA | $150.00 | $91.00 |
$11,284.00
| $40.48 | $10.00 |
315.06.025 | REMOVE SIGN |
0.01
| 9 | EA | $150.00 | $64.00 |
$576.00
| $34.60 | $18.00 |
601.09.011 | TRAFFIC CONTROL |
5.26
| 1 | LS | $150,000.00 | $260,000.00 |
$260,000.00
| $338,228.60 | $260,000.00 |
601.09.019 | CHANGEABLE MESSAGE SIGN |
0.21
| 2 | EA | $5,000.00 | $5,100.00 |
$10,200.00
| $8,450.00 | $7,000.00 |
| TRASH RACK PER DETAIL E ON SHEET 5 |
0.67
| 3 | EA | $6,000.00 | $11,000.00 |
$33,000.00
| $7,640.00 | $8,800.00 |
| TRANSITION RAILING (TYPE WB-31) |
0.51
| 6 | EA | $1,500.00 | $4,200.00 |
$25,200.00
| $4,170.00 | $4,200.00 |
| SAWCUT & REMOVE EXST MASONRY BLOCK HEADWALL |
0.06
| 1 | EA | $2,000.00 | $2,950.00 |
$2,950.00
| $3,620.00 | $3,650.00 |
| REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) |
0.04
| 150 | LF | $30.00 | $13.90 |
$2,085.00
| $13.78 | $13.90 |
| REMOVE AND DISPOSE OF EXISTING 30" CMP |
0.02
| 1 | LF | $125.00 | $765.00 |
$765.00
| $947.40 | $600.00 |
| REMOVE AND DISPOSE OF EXISTING 24" CMP |
0.02
| 1 | LF | $100.00 | $750.00 |
$750.00
| $943.40 | $600.00 |
| REMOVE AND DISPOSE OF EXISTING GUARDRAIL END TREATMENT AND CONCRETE FOOTING (INCLUDING POSTS) |
0.01
| 13 | LF | $45.00 | $54.00 |
$702.00
| $53.20 | $52.00 |
| REMOVE EXST MASONRY BLOCK HEADWALL |
0.08
| 2 | EA | $1,000.00 | $2,000.00 |
$4,000.00
| $3,170.00 | $3,650.00 |
| REMOVE SIGN AND POST |
0.01
| 4 | EA | $150.00 | $107.00 |
$428.00
| $70.20 | $52.00 |
| RAILING DELINEATION, PER CALTRANS STD PLAN A77N4 |
0.01
| 7 | EA | $30.00 | $80.00 |
$560.00
| $79.20 | $76.00 |
| RELOCATE SIGN AND POST |
0.08
| 16 | EA | $300.00 | $240.00 |
$3,840.00
| $189.20 | $175.00 |
| MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) |
0.14
| 188 | LF | $80.00 | $36.50 |
$6,862.00
| $38.00 | $36.50 |
| IN-LINE TERMINAL SYSTEM (TYPE X-TENSION - W/ STEEL POST) |
1.01
| 7 | EA | $4,500.00 | $7,100.00 |
$49,700.00
| $7,050.00 | $7,000.00 |
| FLARED TERMINAL SYSTEM (TYPE SRT-31) |
0.05
| 1 | EA | $4,000.00 | $2,600.00 |
$2,600.00
| $2,740.00 | $2,600.00 |
| FIRE HYDRANT LOCATION RPM |
0.01
| 12 | EA | $20.00 | $32.00 |
$384.00
| $21.60 | $20.00 |
| DETAIL 19 (THERMOPLASTIC) WITH RECESSED MARKERS |
0.13
| 2260 | LF | $2.00 | $2.75 |
$6,215.00
| $2.10 | $2.00 |
| DETAIL 22 (THERMOPLASTIC) WITH RECESSED MARKERS |
1.59
| 46225 | LF | $2.00 | $1.70 |
$78,582.50
| $2.07 | $1.70 |
| DETAIL 29 (THERMOPLASTIC) WITH RECESSED MARKERS |
0.06
| 870 | LF | $4.00 | $3.20 |
$2,784.00
| $3.57 | $3.20 |
| DETAIL 38 (THERMOPLACTIC) WITH RECESSED MARKERS |
0.02
| 520 | LF | $3.00 | $2.25 |
$1,170.00
| $2.75 | $2.50 |
| CRASH CUSHION SYSTEM |
1.78
| 2 | EA | $50,000.00 | $44,000.00 |
$88,000.00
| $40,160.00 | $38,700.00 |
| 24" CMP COUPLER (CALTRANS STD PLAN D97A) |
0.03
| 1 | EA | $120.00 | $1,500.00 |
$1,500.00
| $503.20 | $230.00 |
| 30" CMP COUPLER (CALTRANS STD PLAN D97A) |
0.03
| 1 | EA | $150.00 | $1,600.00 |
$1,600.00
| $535.60 | $290.00 |
| TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE |
0.13
| 2445 | LB | $2.00 | $2.55 |
$6,234.75
| $2.57 | $2.50 |
| Total Percent | 100 | | | | Total Amount | $4,941,981.91 | | |