Bid Price History

La Tuna Fire - Sunset Upper Debris Basin - Debris Flow Barrier Installation
$721,250.00
10/04/2018
534 (A4)
2
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.09.003MOBILIZATION 4.16 1LS$25,000.00$30,000.00 $30,000.00 $41,250.00$41,250.00
300.01.003CLEARING AND GRUBBING 2.70 1LS$5,000.00$19,500.00 $19,500.00 $19,750.00$19,750.00
300.01.057REMOVE EXISTING CHAIN LINK FENCE 1.07 10LF$70.00$775.00 $7,750.00 $562.50$562.50
300.01.067CONCRETE REMOVAL (REINFORCED) 2.15 1CY$1,200.00$15,500.00 $15,500.00 $11,500.00$11,500.00
 DEBRIS FLOW BARRIER 85.20 2EA$340,000.00$307,250.00 $614,500.00 $323,625.00$323,625.00
 ROCK ANCHOR PERFORMANCE TESTING 4.71 4EA$5,000.00$8,500.00 $34,000.00 $8,000.00$8,000.00
 Total Percent100   Total Amount$721,250.00