Bid Price History

Malibu Branch Feeder 30-inch Realignment
$1,163,502.00
10/02/2018
630 (J7),631 (A7)
8
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) 0.17 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.09 2MTH$500.00$500.00 $1,000.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.09 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.003IMPLEMENTATION OF BMPS 1.50 1LS$20,000.00$17,500.00 $17,500.00 $11,625.00$8,750.00
001.07.021SHORING OF OPEN EXCAVATIONS 2.49 1LS$60,400.00$29,000.00 $29,000.00 $84,989.75$54,500.00
001.09.003MOBILIZATION 12.81 1LS$130,000.00$149,000.00 $149,000.00 $100,875.06$98,000.00
306.01.213ABANDON WATERMAIN 1.38 1LS$61,000.00$16,000.00 $16,000.00 $28,250.00$20,500.00
306.01.221AIR RELEASE AND VACUUM VALVE ASSEMBLY, 4" 1.17 1EA$13,000.00$13,600.00 $13,600.00 $14,550.00$14,300.00
306.01.225BUTTERFLY VALVE, 250 PSI WWP, 30" 1.55 1EA$15,000.00$18,000.00 $18,000.00 $45,875.00$38,500.00
500.00.015VIDEO INSPECTION 0.77 1LS$10,000.00$9,000.00 $9,000.00 $6,687.50$5,900.00
601.09.011TRAFFIC CONTROL 3.27 1LS$20,000.00$38,000.00 $38,000.00 $55,850.50$51,500.00
601.09.017FLASHING ARROW SIGN 1.34 2EA$3,000.00$7,800.00 $15,600.00 $5,375.00$5,000.00
601.09.019CHANGEABLE MESSAGE SIGN 0.92 1EA$5,000.00$10,700.00 $10,700.00 $8,056.25$6,750.00
900.02.003PUMP WELL ASSEMBLY, SIDE DRAINING, STD PLAN W-53, STYLE B 0.64 1EA$14,000.00$7,500.00 $7,500.00 $12,462.50$9,500.00
 COLD PLANE ASPHALT CONCRETE PAVEMENT 2.09 24362SF$0.40$1.00 $24,362.00 $0.83$0.88
 REMOVE AND REINSTALL K-RAIL 1.50 600LF$40.00$29.00 $17,400.00 $20.50$19.00
 30" WATERMAIN, 0.375" THICK STEEL, CML&C, WELDED 50.61 1510LF$544.00$390.00 $588,900.00 $721.88$650.00
 TRENCH BACKFILL SLURRY (CLASS 140-S-100) 10.93 1413CY$150.00$90.00 $127,170.00 $127.25$121.50
 OFFICE FACILITIES 1.08 3MTH$4,000.00$4,200.00 $12,600.00 $4,425.00$4,100.00
 CATHODIC PROTECTION ANODE AND TEST STATION 1.12 1EA$6,000.00$13,000.00 $13,000.00 $7,350.00$5,900.00
 JOBS COORDINATOR (ALLOWANCE OF $10,000) 0.86 10000AL$1.00$1.00 $10,000.00 $1.00$1.00
 HMA PAVEMENT 3.19 295TON$115.00$126.00 $37,170.00 $150.88$142.50
 PERMIT AND INSPECTION FEE (ALLOWANCE OF $5,000) 0.43 5000AL$1.00$1.00 $5,000.00 $1.00$1.00
 Total Percent100   Total Amount$1,163,502.00