Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.25
| 0.00 | 0.25 | $15,000.00 | $3,750.00 |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.25
| 0.00 | 0.25 | $25,000.00 | $6,250.00 |
7 | OFFICE FACILITIES | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
8 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $220,000.00 | $110,000.00 |
10 | CONCRETE REMOVAL (NON-REINFORCED) | 100.00 | CY |
61.50
| 0.00 | 61.50 | $450.00 | $27,675.00 |
11 | UNCLASSIFIED EXCAVATION | 549.00 | CY |
114.50
| 0.00 | 114.50 | $180.00 | $20,610.00 |
13 | CRUSHED MISCELLANEOUS BASE | 319.00 | CY |
91.00
| 0.00 | 91.00 | $160.00 | $14,560.00 |
14 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 17.00 | CY |
11.60
| 0.00 | 11.60 | $400.00 | $4,640.00 |
18 | AC PAVEMENT(PATCH BACK) | 34.00 | TON |
22.60
| 0.00 | 22.60 | $300.00 | $6,780.00 |
34 | PCC CURB & GUTTER, TYPE A2-VAR | 204.00 | LF |
204.00
| 0.00 | 204.00 | $75.00 | $15,300.00 |
35 | PCC WALK & DRIVEWAYS, 4" THICK | 2,071.00 | SF |
1,477.00
| 0.00 | 1,477.00 | $13.00 | $19,201.00 |
36 | PCC CURB RAMPS | 30.00 | CY |
19.30
| 0.00 | 19.30 | $1,400.00 | $27,020.00 |
37 | DETECTABLE WARNING SURFACE | 187.00 | SF |
135.00
| 0.00 | 135.00 | $55.00 | $7,425.00 |
39 | CROSS GUTTER | 77.00 | CY |
6.90
| 0.00 | 6.90 | $700.00 | $4,830.00 |
61 | TRAFFIC CONTROL | 1.00 | LS |
0.25
| 0.00 | 0.25 | $200,000.00 | $50,000.00 |
62 | FLASHING ARROW SIGN | 6.00 | EA |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
63 | CHANGEABLE MESSAGE SIGN | 7.00 | EA |
4.00
| 0.00 | 4.00 | $10,000.00 | $40,000.00 |
|