Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Pine Canyon Road
Contractor: All American Asphalt
P.O. Box 2229
Corona, CA 92878-2229
Project ID: RDC0014131
Federal Number(s): None
Original Contract: $3,288,999.00
Awarded: 4/4/2018
Period Ending: 8/20/2018
Board Accepted: 5/22/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF BMPS1.00LS 0.40 0.000.40$6,000.00$2,400.00
5OFFICE FACILITIES5.00MTH 1.00 0.001.00$4,000.00$4,000.00
6MOBILIZATION1.00LS 0.95 0.000.95$229,606.30$218,125.99
7CLEARING AND GRUBBING1.00LS 0.50 0.000.50$5,000.00$2,500.00
16CIR AC PAVEMENT, 3" THICK143,216.00SY 134,628.00 0.00134,628.00$5.70$767,379.60
17EMULSIFIED RECYCLING AGENT550.00TON 550.00 0.00550.00$624.00$343,200.00
18IMPORTED RECLAIMED ASPHALT PAVEMENT (RAP)5,049.00TON 4,782.98 0.004,782.98$40.70$194,667.29
20TRAFFIC CONTROL1.00LS 0.40 0.000.40$116,000.00$46,400.00
21CHANGEABLE MESSAGE SIGN2.00EA 2.00 0.002.00$5,100.00$10,200.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,590,372.88 $0.00 $1,590,372.88
Retained* $79,518.64 $0.00 $79,518.64
Deducted $0.00 $0.00 $0.00
Due $1,510,854.24 $0.00 $1,510,854.24



*This project has an escrow account.

Contact Office Engineer
Hoda Hassan (626) 300-2090
Contractor Copy  
P Please consider the environment before printing this report.