Los Angeles County Public Works
Project Management Division III
Progress Payment 2
Project Name: Pine Canyon Road
Contractor: All American Asphalt
P.O. Box 2229
Corona, CA 92878-2229
Project ID: RDC0014131
Federal Number(s): None
Original Contract: $3,288,999.00
Awarded: 4/4/2018
Period Ending: 9/20/2018
Board Accepted: 5/22/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 2.00 1.001.00$500.00$500.00
5OFFICE FACILITIES5.00MTH 2.00 1.001.00$4,000.00$4,000.00
6MOBILIZATION1.00LS 1.00 0.950.05$229,606.30$11,480.32
7CLEARING AND GRUBBING1.00LS 1.00 0.500.50$5,000.00$2,500.00
8UNCLASSIFIED EXCAVATION180.00CY 100.12 0.00100.12$173.00$17,320.76
11AC PAVEMENT(INVERTED SHOULDERS)610.00TON 610.00 0.00610.00$114.50$69,845.00
12AC PAVEMENT (OVERSIDE DRAINS)21.00TON 21.00 0.0021.00$457.00$9,597.00
13ADJUST MANHOLE2.00EA 2.00 0.002.00$4,500.00$9,000.00
14ASPHALT RUBBER HOT MIX11,772.00TON 10,996.52 0.0010,996.52$104.60$1,150,235.99
15ASPHALT RUBBER HOT MIX (TEST STRIP)500.00TON 500.00 0.00500.00$126.60$63,300.00
20TRAFFIC CONTROL1.00LS 0.90 0.400.50$116,000.00$58,000.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 8.00 0.008.00$100.00 $800.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,986,151.95 $1,590,372.88 $1,395,779.07
Retained* $149,307.60 $79,518.64 $69,788.96
Deducted $800.00 $0.00 $800.00
Due $2,836,044.35 $1,510,854.24 $1,325,190.11



*This project has an escrow account.

Contact Office Engineer
Hoda Hassan (626) 300-2090