Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
5 | OFFICE FACILITIES | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $4,000.00 | $4,000.00 |
6 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $229,606.30 | $11,480.32 |
7 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.50 | 0.50 | $5,000.00 | $2,500.00 |
8 | UNCLASSIFIED EXCAVATION | 180.00 | CY |
100.12
| 0.00 | 100.12 | $173.00 | $17,320.76 |
11 | AC PAVEMENT(INVERTED SHOULDERS) | 610.00 | TON |
610.00
| 0.00 | 610.00 | $114.50 | $69,845.00 |
12 | AC PAVEMENT (OVERSIDE DRAINS) | 21.00 | TON |
21.00
| 0.00 | 21.00 | $457.00 | $9,597.00 |
13 | ADJUST MANHOLE | 2.00 | EA |
2.00
| 0.00 | 2.00 | $4,500.00 | $9,000.00 |
14 | ASPHALT RUBBER HOT MIX | 11,772.00 | TON |
10,996.52
| 0.00 | 10,996.52 | $104.60 | $1,150,235.99 |
15 | ASPHALT RUBBER HOT MIX (TEST STRIP) | 500.00 | TON |
500.00
| 0.00 | 500.00 | $126.60 | $63,300.00 |
20 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.40 | 0.50 | $116,000.00 | $58,000.00 |