Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: El Segundo Boulevard - Avalon Boulevard to Central Avenue, et al.
Contractor: Toro Enterprises, Inc.
P.O. Box 6285
Oxnard, CA 93031
Project ID: RDC0014453
Federal Number(s): None
Original Contract: $2,844,364.47
Awarded: 5/20/2015
Period Ending: 12/1/2015
Board Accepted: 2/28/2017
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 4.00 3.001.00$800.00$800.00
4IMPLEMENTATION OF THE SWPPP1.00LS 0.50 0.400.10$50,000.00$5,000.00
5TRAFFIC CONTROL1.00LS 0.50 0.400.10$79,000.00$7,900.00
9IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.60 0.400.20$7,500.00$1,500.00
11EXCAVATION, TRANSPORTATION, AND DISPOSAL OF LEAD CONTAMINATED SOIL1,240.00TON 810.59 681.12129.47$104.00$13,464.88
13OFFICE FACILITIES1.00LS 0.50 0.400.10$14,000.00$1,400.00
14MOBILIZATION1.00LS 1.00 0.750.25$190,000.00$47,500.00
17CONCRETE REMOVAL (NON-REINFORCED)621.00CY 616.20 611.005.20$135.00$702.00
20CRUSHED MISCELLANEOUS BASE921.00CY 964.30 510.30454.00$83.00$37,682.00
31PCC CURB, TYPE A1-VAR356.00LF 303.50 154.00149.50$12.00$1,794.00
34PCC WALK, DRIVES & CURB RAMPS, 4" THICK42,348.00SF 22,909.25 19,494.253,415.00$3.35$11,440.25

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $945,573.41 $816,390.28 $129,183.13
Retained* $46,403.68 $39,944.52 $6,459.16
Deducted $0.00 $0.00 $0.00
Due $899,169.73 $776,445.76 $122,723.97



*This project has an escrow account.