Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: El Segundo Boulevard - Avalon Boulevard to Central Avenue, et al.
Contractor: Toro Enterprises, Inc.
P.O. Box 6285
Oxnard, CA 93031
Project ID: RDC0014453
Federal Number(s): None
Original Contract: $2,844,364.47
Awarded: 5/20/2015
Period Ending: 6/1/2016
Board Accepted: 2/28/2017
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE SWPPP1.00LS 1.00 0.900.10$50,000.00$5,000.00
5TRAFFIC CONTROL1.00LS 0.95 0.800.15$79,000.00$11,850.00
6FLASHING ARROW SIGN5.00EA 4.00 2.002.00$1,665.00$3,330.00
7CHANGEABLE MESSAGE SIGN8.00EA 6.00 0.006.00$5,330.00$31,980.00
22COLD MILL AC PAVEMENT (> 1-1/2 - 3")558,966.00SF 538,565.00 0.00538,565.00$0.16$86,170.40
26DOUBLE ADJUST MANHOLE54.00EA 51.00 1.0050.00$500.00$25,000.00
27ASPHALT RUBBER HOT MIX (TEST STRIP)500.00TON 492.83 0.00492.83$85.00$41,890.55
28ASPHALT RUBBER HOT MIX4,755.00TON 4,755.00 0.004,755.00$85.00$404,175.00
29COLD-IN-PLACE RECYCLED ASPHALT CONCRETE PAVEMENT, 3" THICK57,280.00SY 55,685.00 0.0055,685.00$4.70$261,719.50
30EMULSIFIED RECYCLING AGENT310.00TON 310.00 0.00310.00$710.00$220,100.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 15.50 6.009.50$100.00 $950.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,718,394.47 $1,627,179.02 $1,091,215.45
Retained* $135,044.73 $80,483.96 $54,560.77
Deducted $1,550.00 $600.00 $950.00
Due $2,581,799.74 $1,546,095.06 $1,035,704.68



*This project has an escrow account.

Contact Office Engineer
Contractor Copy  