Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
4 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 0.90 | 0.10 | $50,000.00 | $5,000.00 |
5 | TRAFFIC CONTROL | 1.00 | LS |
0.95
| 0.80 | 0.15 | $79,000.00 | $11,850.00 |
6 | FLASHING ARROW SIGN | 5.00 | EA |
4.00
| 2.00 | 2.00 | $1,665.00 | $3,330.00 |
7 | CHANGEABLE MESSAGE SIGN | 8.00 | EA |
6.00
| 0.00 | 6.00 | $5,330.00 | $31,980.00 |
22 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 558,966.00 | SF |
538,565.00
| 0.00 | 538,565.00 | $0.16 | $86,170.40 |
26 | DOUBLE ADJUST MANHOLE | 54.00 | EA |
51.00
| 1.00 | 50.00 | $500.00 | $25,000.00 |
27 | ASPHALT RUBBER HOT MIX (TEST STRIP) | 500.00 | TON |
492.83
| 0.00 | 492.83 | $85.00 | $41,890.55 |
28 | ASPHALT RUBBER HOT MIX | 4,755.00 | TON |
4,755.00
| 0.00 | 4,755.00 | $85.00 | $404,175.00 |
29 | COLD-IN-PLACE RECYCLED ASPHALT CONCRETE PAVEMENT, 3" THICK | 57,280.00 | SY |
55,685.00
| 0.00 | 55,685.00 | $4.70 | $261,719.50 |
30 | EMULSIFIED RECYCLING AGENT | 310.00 | TON |
310.00
| 0.00 | 310.00 | $710.00 | $220,100.00 |