Los Angeles County Public Works
Project Management Division III
Progress Payment 11
Project Name: El Segundo Boulevard - Avalon Boulevard to Central Avenue, et al.
Contractor: Toro Enterprises, Inc.
P.O. Box 6285
Oxnard, CA 93031
Project ID: RDC0014453
Federal Number(s): None
Original Contract: $2,844,364.47
Awarded: 5/20/2015
Period Ending: 8/2/2016
Board Accepted: 2/28/2017
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
93DETAIL 9 (THERMOPLASTIC)13,875.00LF 13,875.00 10,000.003,875.00$0.35$1,356.25
94DETAIL 22 (THERMOPLASTIC)959.00LF 959.00 500.00459.00$0.95$436.05
95DETAIL 25A (THERMOPLASTIC)2,633.00LF 2,633.00 1,500.001,133.00$0.46$521.18
96DETAIL 27B (THERMOPLASTIC)5,132.00LF 5,132.00 4,000.001,132.00$0.40$452.80
97DETAIL 29 (THERMOPLASTIC)94.00LF 94.00 80.0014.00$2.00$28.00
98DETAIL 32 (THERMOPLASTIC)3,617.00LF 3,375.00 2,500.00875.00$2.00$1,750.00
99DETAIL 37B (THERMOPLASTIC)480.00LF 480.00 0.00480.00$1.05$504.00
100DETAIL 38 (THERMOPLASTIC)1,970.00LF 1,970.00 1,000.00970.00$1.05$1,018.50
101DETAIL 39 (THERMOPLASTIC)15,230.00LF 15,111.00 13,000.002,111.00$0.67$1,414.37
102DETAIL 39A (THERMOPLASTIC)2,644.00LF 2,644.00 1,500.001,144.00$0.67$766.48
103PAVEMENT MARKINGS (THERMOPLASTIC)700.00SF 700.00 600.00100.00$4.15$415.00
1056" STRIPING (THERMOPLASTIC)636.00LF 636.00 500.00136.00$1.25$170.00
10612" STRIPING (THERMOPLASTIC)1,994.00LF 1,994.00 1,500.00494.00$3.15$1,556.10
10724" STRIPING (THERMOPLASTIC)271.00LF 215.00 100.00115.00$6.25$718.75
108INSTALL FIRE HYDRANT LOCATION RPM31.00EA 31.00 0.0031.00$10.40$322.40
109REMOVE PAVEMENT MARKINGS (PAINT)45.00SF 45.00 0.0045.00$2.60$117.00
110REMOVE STRIPING AND MARKINGS (PAINT)1,033.00SF 196.00 400.00-204.00$2.60($530.40)

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,916,482.25 $2,905,465.77 $11,016.48
Retained* $72,474.55 $72,199.14 $275.41
Deducted $1,950.00 $1,950.00 $0.00
Due $2,842,057.70 $2,831,316.63 $10,741.07



*This project has an escrow account.