Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
2 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |