Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
3 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.75 | 0.15 | $11,000.00 | $1,650.00 |
4 | RESTORATION OF EXISTING IMPROVEMENTS | 1.00 | LS |
0.80
| 0.60 | 0.20 | $10,000.00 | $2,000.00 |
5 | TRAFFIC CONTROL | 1.00 | LS |
0.80
| 0.60 | 0.20 | $65,000.00 | $13,000.00 |
8 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 0.00 | 1.00 | $15,000.00 | $15,000.00 |
10 | OFFICE FACILITIES | 1.00 | LS |
0.90
| 0.75 | 0.15 | $7,500.00 | $1,125.00 |
11 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $130,000.00 | $6,500.00 |
12 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.75 | 0.25 | $100,000.00 | $25,000.00 |
13 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 38.00 | EA |
38.00
| 25.00 | 13.00 | $600.00 | $7,800.00 |
14 | CONCRETE REMOVAL (NON-REINFORCED) | 2,271.00 | CY |
1,873.10
| 1,127.23 | 745.87 | $65.00 | $48,481.55 |
16 | UNCLASSIFIED EXCAVATION | 6,509.00 | CY |
5,655.42
| 4,514.63 | 1,140.79 | $46.00 | $52,476.34 |
17 | STABILIZATION GEOTEXTILE | 1,023.00 | SY |
644.44
| 0.00 | 644.44 | $6.00 | $3,866.64 |
18 | CRUSHED MISCELLANEOUS BASE | 5,465.00 | CY |
3,634.78
| 2,654.58 | 980.20 | $55.00 | $53,911.00 |
20 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 153.00 | CY |
153.04
| 104.00 | 49.04 | $220.00 | $10,788.80 |
22 | AC PAVEMENT | 1,037.00 | TON |
700.00
| 500.00 | 200.00 | $82.50 | $16,500.00 |
23 | AC PAVEMENT(PATCH BACK) | 167.00 | TON |
209.75
| 168.00 | 41.75 | $175.00 | $7,306.25 |
28 | PCC PAVEMENT | 231.00 | CY |
148.00
| 0.00 | 148.00 | $250.00 | $37,000.00 |
46 | CONCRETE BLOCK SLOUGH WALL PER STD PLAN 622 | 126.00 | SF |
126.00
| 60.00 | 66.00 | $50.00 | $3,300.00 |
47 | PCC FOOTING FOR CONCRETE BLOCK SLOUGH WALL | 3.00 | CY |
3.00
| 2.00 | 1.00 | $750.00 | $750.00 |
48 | PCC CURB, TYPE A1-8 | 210.00 | LF |
185.50
| 0.00 | 185.50 | $18.00 | $3,339.00 |
50 | PCC CURB & GUTTER, TYPE A2-8 | 4,051.00 | LF |
4,326.00
| 3,583.00 | 743.00 | $25.50 | $18,946.50 |
54 | PCC WALK, DRIVES & CURB RAMPS, 4" THICK | 100,163.00 | SF |
96,244.51
| 62,570.51 | 33,674.00 | $4.50 | $151,533.00 |
55 | PCC DRIVEWAYS, 6" THICK | 10,639.00 | SF |
7,046.50
| 2,245.50 | 4,801.00 | $6.00 | $28,806.00 |
56 | DETECTABLE WARNING SURFACE | 1,275.00 | SF |
795.00
| 597.00 | 198.00 | $25.00 | $4,950.00 |
57 | CROSS GUTTER | 200.00 | CY |
217.00
| 200.00 | 17.00 | $325.00 | $5,525.00 |
58 | CROSS GUTTER (MOD) | 45.00 | CY |
45.00
| 0.00 | 45.00 | $325.00 | $14,625.00 |
59 | ALLEY INTERSECTION | 40.00 | CY |
17.83
| 11.32 | 6.51 | $325.00 | $2,115.75 |
64 | ABANDON EXISTING CMP AND CATCH BASIN | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
74 | NO. 6 PULL BOX INCL PCC COVER | 32.00 | EA |
19.00
| 17.00 | 2.00 | $675.00 | $1,350.00 |
84 | INSTALL TYPE 332 CABINET | 1.00 | EA |
1.00
| 0.00 | 1.00 | $900.00 | $900.00 |
85 | TYPE 332 CABINET AND 170 ATC/HC11 CONTROLLER (COMPLETE) | 2.00 | EA |
2.00
| 0.00 | 2.00 | $12,000.00 | $24,000.00 |
87 | TYPE 1 STANDARD | 3.00 | EA |
3.00
| 0.00 | 3.00 | $600.00 | $1,800.00 |
88 | TYPE 15 STANDARD | 7.00 | EA |
4.00
| 0.00 | 4.00 | $2,100.00 | $8,400.00 |
89 | TYPE 19 STANDARD | 6.00 | EA |
4.00
| 0.00 | 4.00 | $6,000.00 | $24,000.00 |
93 | 25' SIGNAL MAST ARM | 27.00 | EA |
4.00
| 0.00 | 4.00 | $2,200.00 | $8,800.00 |
94 | 8' LUMINAIRE MAST ARM | 2.00 | EA |
1.00
| 0.00 | 1.00 | $700.00 | $700.00 |
95 | 12' LUMINAIRE MAST ARM | 11.00 | EA |
7.00
| 0.00 | 7.00 | $730.00 | $5,110.00 |
97 | 150 W HPS LUMINAIRE | 11.00 | EA |
8.00
| 0.00 | 8.00 | $400.00 | $3,200.00 |
102 | 3-12" LED VEHICLE HEAD (COMPLETE) | 26.00 | EA |
15.00
| 0.00 | 15.00 | $700.00 | $10,500.00 |
103 | LED PEDESTRIAN HEAD (COMPLETE) | 16.00 | EA |
11.00
| 0.00 | 11.00 | $600.00 | $6,600.00 |
S-01 | POTHOLING UNDER 5' DEEP | | STIP |
33.00
| 4.00 | 29.00 | $300.00 | $8,700.00 |
S-02 | POTHOLING OVER 5' DEEP | | EA |
3.00
| 1.00 | 2.00 | $500.00 | $1,000.00 |
S-05 | AC PAVEMENT (PATCH BACK) OVER 125% | | TON |
254.42
| 150.00 | 104.42 | $165.00 | $17,229.30 |
|