Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.25
| 0.00 | 0.25 | $5,000.00 | $1,250.00 |
5 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.00 | 0.30 | $60,000.00 | $18,000.00 |
6 | PREPARATION OF TRAFFIC CONTROL PLANS (CITIES) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
8 | FLASHING ARROW SIGN | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,100.00 | $2,200.00 |
9 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
2.00
| 0.00 | 2.00 | $3,100.00 | $6,200.00 |
10 | OFFICE FACILITIES | 1.00 | LS |
0.25
| 0.00 | 0.25 | $10,000.00 | $2,500.00 |
11 | MOBILIZATION | 1.00 | LS |
0.25
| 0.00 | 0.25 | $70,680.44 | $17,670.11 |
13 | CONCRETE REMOVAL (NON-REINFORCED) | 347.00 | CY |
199.61
| 0.00 | 199.61 | $200.00 | $39,922.00 |
15 | UNCLASSIFIED EXCAVATION | 1,095.00 | CY |
236.06
| 0.00 | 236.06 | $92.00 | $21,717.52 |
18 | CRUSHED MISCELLANEOUS BASE | 522.00 | CY |
193.55
| 0.00 | 193.55 | $95.00 | $18,387.25 |
19 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 35.00 | CY |
16.92
| 0.00 | 16.92 | $110.00 | $1,861.20 |
26 | PCC PAVEMENT (BUS PAD) | 98.00 | CY |
66.85
| 0.00 | 66.85 | $350.00 | $23,397.50 |
32 | PCC CURB & GUTTER, TYPE A2-8 | 1,455.00 | LF |
569.33
| 0.00 | 569.33 | $27.00 | $15,371.91 |
34 | PCC WALK, DRIVES & CURB RAMPS, 4" THICK | 15,767.00 | SF |
5,927.46
| 0.00 | 5,927.46 | $5.60 | $33,193.78 |
36 | CROSS GUTTER | 49.00 | CY |
32.33
| 0.00 | 32.33 | $345.00 | $11,153.85 |
37 | ALLEY INTERSECTION | 6.00 | CY |
4.44
| 0.00 | 4.44 | $376.00 | $1,669.44 |
|