Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Firestone Boulevard - Central Avenue/Graham Avenue, et al.
Contractor: All American Asphalt
P.O. Box 2229
Corona, CA 92878-2229
Project ID: RDC0014915
Federal Number(s): None
Original Contract: $2,346,000.00
Awarded: 4/7/2016
Period Ending: 2/3/2017
Board Accepted: 9/19/2017
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH)3.00MTH 2.00 1.001.00$500.00$500.00
4IMPLEMENTATION OF BMPS1.00LS 0.75 0.500.25$5,000.00$1,250.00
5TRAFFIC CONTROL1.00LS 0.75 0.500.25$60,000.00$15,000.00
10OFFICE FACILITIES1.00LS 0.75 0.500.25$10,000.00$2,500.00
11MOBILIZATION1.00LS 0.75 0.500.25$70,680.44$17,670.11
20COLD MILL AC PAVEMENT (> 1-1/2 - 3")681,000.00SF 98,190.00 0.0098,190.00$0.15$14,728.50
23AC PAVEMENT(LEVELING COURSE)169.00TON 142.15 0.00142.15$82.00$11,656.30
482" CONDUIT (SCH 80 PVC)1,345.00LF 1,345.00 780.00565.00$31.30$17,684.50
493" CONDUIT (SCH 80 PVC)555.00LF 439.00 125.00314.00$70.00$21,980.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 106.00 61.0045.00$1,000.00 $45,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $637,860.35 $534,890.94 $102,969.41
Retained* $31,893.04 $26,744.55 $5,148.49
Deducted $106,000.00 $61,000.00 $45,000.00
Due $499,967.31 $447,146.39 $52,820.92



*This project has an escrow account.