Los Angeles County Public Works
Project Management Division III
Progress Payment 6
Project Name: Firestone Boulevard - Central Avenue/Graham Avenue, et al.
Contractor: All American Asphalt
P.O. Box 2229
Corona, CA 92878-2229
Project ID: RDC0014915
Federal Number(s): None
Original Contract: $2,346,000.00
Awarded: 4/7/2016
Period Ending: 5/1/2017
Board Accepted: 9/19/2017
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF BMPS1.00LS 1.00 0.950.05$5,000.00$250.00
5TRAFFIC CONTROL1.00LS 1.00 0.950.05$60,000.00$3,000.00
10OFFICE FACILITIES1.00LS 1.00 0.950.05$10,000.00$500.00
11MOBILIZATION1.00LS 1.00 0.950.05$70,680.44$3,534.02
14CONCRETE REMOVAL (REINFORCED)5.00CY 5.00 0.005.00$500.00$2,500.00
15UNCLASSIFIED EXCAVATION1,095.00CY 922.51 897.0625.45$92.00$2,341.40
18CRUSHED MISCELLANEOUS BASE522.00CY 522.00 519.552.45$95.00$232.75
27ASPHALT RUBBER HOT MIX5,879.00TON 5,879.00 4,034.531,844.47$80.00$147,557.60
34PCC WALK, DRIVES & CURB RAMPS, 4" THICK15,767.00SF 15,767.00 15,157.62609.38$5.60$3,412.53
38FURNISH AND PLANT 15 GALLON TREE13.00EA 12.00 11.001.00$415.00$415.00
493" CONDUIT (SCH 80 PVC)555.00LF 555.00 439.00116.00$70.00$8,120.00
51NO. 5 PULL BOX INCL PCC COVER5.00EA 5.00 4.001.00$303.00$303.00
52NO. 6 PULL BOX INCL PCC COVER11.00EA 11.00 9.002.00$606.00$1,212.00
53INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT13,805.00LF 11,427.00 0.0011,427.00$9.29$106,156.83
542-CAMERA VIDEO DETECTION SYSTEM (COMPLETE)1.00LS 1.00 0.001.00$25,500.00$25,500.00
553-CAMERA VIDEO DETECTION SYSTEM (COMPLETE)1.00LS 1.00 0.001.00$37,700.00$37,700.00
57REMOVE VEHICLE HEAD (COMPLETE)25.00EA 17.00 0.0017.00$152.00$2,584.00
58REMOVE PEDESTRIAN HEAD (COMPLETE)31.00EA 31.00 0.0031.00$101.00$3,131.00
59REMOVE PEDESTRIAN PUSH BUTTON31.00EA 31.00 0.0031.00$51.00$1,581.00
64PEDESTRIAN PUSH BUTTON32.00EA 32.00 0.0032.00$76.00$2,432.00
65PEDESTRIAN PUSH BUTTON PLATE32.00EA 32.00 0.0032.00$16.00$512.00
663-12" LED VEHICLE HEAD (COMPLETE) 29.00EA 21.00 0.0021.00$780.00$16,380.00
67LED PEDESTRIAN HEAD (COMPLETE) 32.00EA 32.00 0.0032.00$505.00$16,160.00
68DETAIL 8 (THERMOPLASTIC)240.00LF 174.00 0.00174.00$1.01$175.74
69DETAIL 9 (THERMOPLASTIC)21,515.00LF 19,722.00 0.0019,722.00$0.45$8,874.90
70DETAIL 21 (THERMOPLASTIC)150.00LF 128.00 0.00128.00$4.04$517.12
71DETAIL 22 (THERMOPLASTIC)6,967.00LF 6,967.00 0.006,967.00$1.21$8,430.07
72DETAIL 27B (THERMOPLASTIC)29,320.00LF 26,214.00 0.0026,214.00$0.30$7,864.20
73DETAIL 29 (THERMOPLASTIC)1,725.00LF 728.00 0.00728.00$1.62$1,179.36
75DETAIL 37B (THERMOPLASTIC)1,855.00LF 1,855.00 0.001,855.00$1.16$2,151.80
76DETAIL 38 (THERMOPLASTIC)6,215.00LF 5,305.00 0.005,305.00$1.11$5,888.55
77DETAIL 38A (THERMOPLASTIC)525.00LF 523.00 0.00523.00$1.31$685.13
78DETAIL 39 (THERMOPLASTIC)29,390.00LF 26,668.00 0.0026,668.00$0.40$10,667.20
79DETAIL 39A (THERMOPLASTIC)22,915.00LF 22,915.00 0.0022,915.00$0.61$13,978.15
80DETAIL 40 (THERMOPLASTIC)685.00LF 287.00 0.00287.00$1.62$464.94
81DETAIL 41 (THERMOPLASTIC)430.00LF 203.00 0.00203.00$1.62$328.86
82PAVEMENT MARKINGS (THERMOPLASTIC)6,275.00SF 6,275.00 0.006,275.00$5.05$31,688.75
836" STRIPING (THERMOPLASTIC)825.00LF 328.00 0.00328.00$1.01$331.28
848" STRIPING (THERMOPLASTIC)3,320.00LF 1,358.00 0.001,358.00$0.96$1,303.68
8512" STRIPING (THERMOPLASTIC)5,135.00LF 4,550.00 0.004,550.00$2.52$11,466.00
8624" STRIPING (THERMOPLASTIC)595.00LF 360.00 0.00360.00$4.75$1,710.00
87CURB MARKINGS (ONE-COAT PAINT)1,375.00LF 1,183.00 0.001,183.00$0.81$958.23
98INSTALL FIRE HYDRANT LOCATION RPM24.00EA 24.00 0.0024.00$25.25$606.00
S-02REMOVE AND REINSTALL TRAFFIC SENSORS LS 1.00 0.500.50$21,275.00$10,637.50
S-3REMOVE DETAIL 8 (THERMO) LF 10,100.00 0.0010,100.00$0.41$4,141.00
S-4REMOVE DETAIL 9 (THERMO) LF 22,370.00 0.0022,370.00$0.47$10,513.90
S-6REMOVE DETAIL 22 (THERMO) LF 5,555.00 0.005,555.00$1.34$7,443.70
S-7REMOVE DETAIL 37B (THERMO) LF 449.00 0.00449.00$1.22$547.78
S-8REMOVE DETAIL 38 (THERMO) LF 220.00 0.00220.00$1.30$286.00
S-10REMOVE DETAIL 40 (THERMO) LF 645.00 0.00645.00$2.33$1,502.85
S-11REMOVE PAVEMENT MARKINGS (THERMO) SF 1,665.00 0.001,665.00$5.82$9,690.30
S-12REMOVE 12" STRIPING (THERMO) LF 118.00 0.00118.00$3.49$411.82
S-14INSTALL 12 & 3 CONDUCTOR WIRING @ FIRESTONE AND COMPTON T&M 10,000.00 0.0010,000.00$1.00$10,000.00
S-15INSTALL 12 & 3 CONDUCTOR WIRING AT LA CIENEGA AND 120TH  T&M 10,000.00 0.0010,000.00$1.00$10,000.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 190.00 154.0036.00$1,000.00 $36,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,219,795.44 $1,659,835.50 $559,959.94
Retained* $110,989.80 $82,991.78 $27,998.02
Deducted $190,000.00 $154,000.00 $36,000.00
Due $1,918,805.64 $1,422,843.72 $495,961.92



*This project has an escrow account.

Contact Office Engineer
Robert Eisenhamer (626) 458-3155
Contractor Copy  
P Please consider the environment before printing this report.