Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
13 | CONCRETE REMOVAL (NON-REINFORCED) | 1,330.00 | CY |
1,310.73
| 1,134.73 | 176.00 | $129.00 | $22,704.00 |
14 | UNCLASSIFIED EXCAVATION | 9,105.00 | CY |
1,397.75
| 1,263.10 | 134.65 | $48.00 | $6,463.20 |
15 | CRUSHED MISCELLANEOUS BASE | 1,525.00 | CY |
1,380.21
| 1,263.10 | 117.11 | $58.00 | $6,792.38 |
30 | PCC CURB & GUTTER, TYPE A2-8 | 1,717.00 | LF |
2,017.00
| 1,717.00 | 300.00 | $18.00 | $5,400.00 |
31 | PCC WALK, DRIVES & CURB RAMPS, 4" THICK | 49,973.00 | SF |
43,328.18
| 42,385.00 | 943.18 | $3.35 | $3,159.65 |
32 | PCC DRIVEWAYS, 6" THICK | 2,114.00 | SF |
962.00
| 931.60 | 30.40 | $5.00 | $152.00 |
34 | CROSS GUTTER | 441.00 | CY |
418.29
| 374.24 | 44.05 | $206.00 | $9,074.30 |