Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
4.00
| 3.00 | 1.00 | $700.00 | $700.00 |
4 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.65
| 0.50 | 0.15 | $48,000.00 | $7,200.00 |
5 | TRAFFIC CONTROL | 1.00 | LS |
0.65
| 0.45 | 0.20 | $69,000.00 | $13,800.00 |
6 | OFFICE FACILITIES | 1.00 | LS |
0.75
| 0.70 | 0.05 | $17,000.00 | $850.00 |
7 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $215,000.00 | $10,750.00 |
8 | CLEARING AND GRUBBING | 1.00 | LS |
0.65
| 0.50 | 0.15 | $6,500.00 | $975.00 |
14 | UNCLASSIFIED EXCAVATION | 9,105.00 | CY |
3,713.32
| 1,617.38 | 2,095.94 | $48.00 | $100,605.12 |
18 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 907,641.00 | SF |
452,724.00
| 0.00 | 452,724.00 | $0.13 | $58,854.12 |
22 | DOUBLE ADJUST MANHOLE | 158.00 | EA |
67.00
| 0.00 | 67.00 | $435.00 | $29,145.00 |