Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
4 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.70
| 0.65 | 0.05 | $48,000.00 | $2,400.00 |
5 | TRAFFIC CONTROL | 1.00 | LS |
0.70
| 0.65 | 0.05 | $69,000.00 | $3,450.00 |
8 | CLEARING AND GRUBBING | 1.00 | LS |
0.70
| 0.65 | 0.05 | $6,500.00 | $325.00 |
14 | UNCLASSIFIED EXCAVATION | 9,105.00 | CY |
8,652.74
| 3,713.32 | 4,939.42 | $48.00 | $237,092.16 |
18 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 907,641.00 | SF |
644,750.00
| 452,724.00 | 192,026.00 | $0.13 | $24,963.38 |
25 | COLD CENTRAL PLANT RECYCLED ASPHALT CONCRETE PAVEMENT (CCPRACP), 3" THICK | 100,850.00 | SY |
32,626.66
| 0.00 | 32,626.66 | $4.60 | $150,082.64 |
26 | EMULSIFIED RECYCLING AGENT | 513.00 | TON |
136.92
| 0.00 | 136.92 | $742.00 | $101,594.64 |