Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
4 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 0.95 | 0.05 | $48,000.00 | $2,400.00 |
5 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.95 | 0.05 | $69,000.00 | $3,450.00 |
22 | DOUBLE ADJUST MANHOLE | 158.00 | EA |
139.00
| 71.00 | 68.00 | $435.00 | $29,580.00 |
S-7 | STABILIZE UNSUITABLE SUBGRADE MATERIAL | | T&M |
70,000.00
| 55,000.00 | 15,000.00 | $1.00 | $15,000.00 |
S-14 | EQUIPMENT STANDBY & DUST CONTROL | | T&M |
58,000.00
| 35,000.00 | 23,000.00 | $1.00 | $23,000.00 |
S-15 | COLD MILL 1.75 " & HAUL AWAY | | SF |
156,651.00
| 147,331.00 | 9,320.00 | $0.38 | $3,541.60 |
S-17 | 8 INCHES OF CEMENT STABILIZED PULVERIZED BASE | | SF |
156,651.00
| 147,331.00 | 9,320.00 | $1.02 | $9,506.40 |
S-20 | PRIME COAT OVER CSPB AREA | | SF |
378,400.00
| 374,538.00 | 3,862.00 | $0.09 | $347.58 |