Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.30
| 0.15 | 0.15 | $15,000.00 | $2,250.00 |
6 | OFFICE FACILITIES | 1.00 | LS |
0.30
| 0.15 | 0.15 | $50,000.00 | $7,500.00 |
7 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $250,000.00 | $125,000.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.30
| 0.15 | 0.15 | $135,000.00 | $20,250.00 |
11 | CONCRETE REMOVAL (NON-REINFORCED) | 756.00 | CY |
83.22
| 6.00 | 77.22 | $60.00 | $4,633.20 |
12 | UNCLASSIFIED EXCAVATION | 3,350.00 | CY |
875.76
| 812.00 | 63.76 | $50.00 | $3,188.00 |
14 | CRUSHED MISCELLANEOUS BASE | 692.00 | CY |
69.64
| 6.00 | 63.64 | $35.00 | $2,227.40 |
30 | PCC CURB & GUTTER, TYPE A2-6 | 61.00 | LF |
21.00
| 0.00 | 21.00 | $27.00 | $567.00 |
31 | PCC CURB & GUTTER, TYPE A2-8 | 4,654.00 | LF |
694.00
| 0.00 | 694.00 | $28.00 | $19,432.00 |
32 | PCC CURB & GUTTER, TYPE A2-VAR | 408.00 | LF |
46.00
| 0.00 | 46.00 | $28.00 | $1,288.00 |
33 | PCC WALK & DRIVEWAYS, 4" THICK | 9,332.00 | SF |
766.00
| 0.00 | 766.00 | $4.00 | $3,064.00 |
36 | CROSS GUTTER | 365.00 | CY |
24.00
| 0.00 | 24.00 | $600.00 | $14,400.00 |
43 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.15 | 0.15 | $260,000.00 | $39,000.00 |
45 | LID-A, BIO-SWALE | 38.00 | EA |
24.00
| 14.00 | 10.00 | $400.00 | $4,000.00 |
46 | LID-B, INFILTRATION UNIT | 2.00 | EA |
1.00
| 0.00 | 1.00 | $1,600.00 | $1,600.00 |