Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $2,000.00 | $0.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
5.00
| 3.00 | 2.00 | $500.00 | $1,000.00 |
3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
4 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 1.00 | 0.00 | $15,000.00 | $0.00 |
6 | OFFICE FACILITIES | 1.00 | LS |
1.00
| 1.00 | 0.00 | $50,000.00 | $0.00 |
7 | MOBILIZATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $250,000.00 | $0.00 |
8 | CITY PERMITS AND INSPECTION FEES (ALLOWANCE OF $15,000) | 15,000.00 | AL |
1,068.00
| 1,068.00 | 0.00 | $1.00 | $0.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 1.00 | 0.00 | $135,000.00 | $0.00 |
10 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 25.00 | EA |
15.00
| 15.00 | 0.00 | $375.00 | $0.00 |
11 | CONCRETE REMOVAL (NON-REINFORCED) | 756.00 | CY |
702.00
| 702.00 | 0.00 | $60.00 | $0.00 |
12 | UNCLASSIFIED EXCAVATION | 3,350.00 | CY |
2,961.00
| 2,961.00 | 0.00 | $50.00 | $0.00 |
13 | UNCLASSIFIED EXCAVATION (ROADWAY) | 7,256.00 | CY |
6,893.42
| 6,893.42 | 0.00 | $40.00 | $0.00 |
14 | CRUSHED MISCELLANEOUS BASE | 692.00 | CY |
642.70
| 642.70 | 0.00 | $35.00 | $0.00 |
15 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 3.00 | CY |
0.00
| 0.00 | 0.00 | $150.00 | $0.00 |
16 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 83,518.00 | SY |
82,961.00
| 82,961.00 | 0.00 | $4.50 | $0.00 |
17 | PORTLAND CEMENT FOR CSPB | 1,627.00 | TON |
1,735.85
| 1,735.85 | 0.00 | $140.00 | $0.00 |
18 | PRIME/TACK COAT FOR CSPB | 12,522.00 | GAL |
9,000.00
| 9,000.00 | 0.00 | $3.50 | $0.00 |
19 | COLD MILL AC PAVEMENT (0 - 1-1/2") | 123,365.00 | SF |
95,328.00
| 95,328.00 | 0.00 | $0.15 | $0.00 |
20 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 681,866.00 | SF |
681,866.00
| 681,866.00 | 0.00 | $0.25 | $0.00 |
21 | AC PAVEMENT(PATCH BACK) | 3.00 | TON |
3.00
| 3.00 | 0.00 | $500.00 | $0.00 |
22 | RECONSTRUCT MANHOLE | 73.00 | EA |
72.00
| 72.00 | 0.00 | $800.00 | $0.00 |
23 | DOUBLE ADJUST MANHOLE | 6.00 | EA |
5.00
| 5.00 | 0.00 | $500.00 | $0.00 |
24 | ASPHALT RUBBER HOT MIX | 6,610.00 | TON |
6,858.00
| 6,858.00 | 0.00 | $78.00 | $0.00 |
25 | ASPHALT RUBBER HOT MIX (TEST STRIP) | 500.00 | TON |
500.00
| 500.00 | 0.00 | $90.00 | $0.00 |
26 | COLD CENTRAL PLANT RECYCLED ASPHALT CONCRETE PAVEMENT (CCPRACP), 3" THICK | 83,518.00 | SY |
82,961.00
| 82,961.00 | 0.00 | $6.00 | $0.00 |
27 | IMPORT RECLAIMED ASPHALT PAVEMENT (RAP) | 3,400.00 | TON |
2,200.00
| 2,200.00 | 0.00 | $10.00 | $0.00 |
28 | EMULSIFIED RECYCLING AGENT | 450.00 | TON |
426.09
| 426.09 | 0.00 | $700.00 | $0.00 |
29 | CONCRETE SLOUGH WALL | 4.00 | CY |
3.51
| 3.51 | 0.00 | $1,000.00 | $0.00 |
30 | PCC CURB & GUTTER, TYPE A2-6 | 61.00 | LF |
53.00
| 53.00 | 0.00 | $27.00 | $0.00 |
31 | PCC CURB & GUTTER, TYPE A2-8 | 4,654.00 | LF |
3,078.30
| 3,078.30 | 0.00 | $28.00 | $0.00 |
32 | PCC CURB & GUTTER, TYPE A2-VAR | 408.00 | LF |
391.00
| 391.00 | 0.00 | $28.00 | $0.00 |
33 | PCC WALK & DRIVEWAYS, 4" THICK | 9,332.00 | SF |
9,300.00
| 9,300.00 | 0.00 | $4.00 | $0.00 |
34 | PCC CURB RAMPS | 28.00 | CY |
68.00
| 68.00 | 0.00 | $600.00 | $0.00 |
35 | DETECTABLE WARNING SURFACE | 560.00 | SF |
444.00
| 444.00 | 0.00 | $20.00 | $0.00 |
36 | CROSS GUTTER | 365.00 | CY |
365.00
| 365.00 | 0.00 | $600.00 | $0.00 |
37 | RIVER ROCK PAVING, 6" THICK | 19,031.00 | SF |
16,575.00
| 16,575.00 | 0.00 | $6.50 | $0.00 |
38 | PERVIOUS CONCRETE, 6" THICK | 29,976.00 | SF |
27,170.00
| 27,170.00 | 0.00 | $5.00 | $0.00 |
39 | NO. 3 CONCRETE AGGREGATE | 555.00 | CY |
503.15
| 503.15 | 0.00 | $85.00 | $0.00 |
40 | METAL HAND RAILINGS PER STD PLAN 606 | 69.00 | LF |
69.00
| 69.00 | 0.00 | $100.00 | $0.00 |
41 | INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT | 1,500.00 | LF |
932.00
| 932.00 | 0.00 | $7.00 | $0.00 |
42 | INSTALL FIRE HYDRANT LOCATION RPM | 10.00 | EA |
37.00
| 37.00 | 0.00 | $25.00 | $0.00 |
43 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 1.00 | 0.00 | $260,000.00 | $0.00 |
44 | FLASHING ARROW SIGN | 2.00 | EA |
2.00
| 2.00 | 0.00 | $4,000.00 | $0.00 |
45 | LID-A, BIO-SWALE | 38.00 | EA |
38.00
| 38.00 | 0.00 | $400.00 | $0.00 |
46 | LID-B, INFILTRATION UNIT | 2.00 | EA |
2.00
| 2.00 | 0.00 | $1,600.00 | $0.00 |
47 | AGRONOMIC SOIL REPORTS | 5.00 | EA |
5.00
| 2.00 | 3.00 | $1,300.00 | $3,900.00 |
48 | LANDSCAPING | 1.00 | LS |
1.00
| 1.00 | 0.00 | $58,000.00 | $0.00 |
49 | IRRIGATION SYSTEM | 1.00 | LS |
1.00
| 1.00 | 0.00 | $140,000.00 | $0.00 |
50 | PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
1.00
| 0.00 | 1.00 | $16,000.00 | $16,000.00 |
S-1 | REVISED MOVE-IN PERIOD | | WD |
25.00
| 25.00 | 0.00 | $0.00 | $0.00 |
S-2 | INSTALLATION OF 135 ADDITIONAL SHRUBS | | LS |
1.00
| 1.00 | 0.00 | $1,225.00 | $0.00 |
S-3 | SUPPLY AND INSTALL 134 TONS OF 2-INCH MINUS ROCK | | LS |
21,036.00
| 21,036.00 | 0.00 | $1.00 | $0.00 |
S-04 | ADDITIONAL WORKING DAYS | | WD |
0.00
| 0.00 | 0.00 | $0.00 | $0.00 |
S-05 | SEWER SPILL REIMBURSEMENT | | LS |
1.00
| 1.00 | 0.00 | ($2,285.00) | $0.00 |
|