Los Angeles County Public Works
Project Management Division III
As-Built 10
Project Name: Ballentine Place, et al.
Contractor: Gentry Brothers, Inc.
384 East Live Oak Avenue
Irwindale, CA 91706-1313
Project ID: RDC0015528
Federal Number(s): None
Original Contract: $4,600,159.75
Awarded: 2/5/2018
Period Ending: 6/18/2019
Board Accepted: 6/25/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000)1.00LS 1.00 1.000.00$2,000.00$0.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)6.00MTH 5.00 5.000.00$500.00$0.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 1.000.00$1,000.00$0.00
4PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 1.000.00$5,000.00$0.00
5IMPLEMENTATION OF THE SWPPP1.00LS 1.00 1.000.00$15,000.00$0.00
6OFFICE FACILITIES1.00LS 1.00 1.000.00$50,000.00$0.00
7MOBILIZATION1.00LS 1.00 1.000.00$250,000.00$0.00
8CITY PERMITS AND INSPECTION FEES (ALLOWANCE OF $15,000)15,000.00AL 1,068.00 1,068.000.00$1.00$0.00
9CLEARING AND GRUBBING1.00LS 1.00 1.000.00$135,000.00$0.00
10ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER)25.00EA 15.00 15.000.00$375.00$0.00
11CONCRETE REMOVAL (NON-REINFORCED)756.00CY 702.00 702.000.00$60.00$0.00
12UNCLASSIFIED EXCAVATION3,350.00CY 2,961.00 2,961.000.00$50.00$0.00
13UNCLASSIFIED EXCAVATION (ROADWAY)7,256.00CY 6,893.42 6,893.420.00$40.00$0.00
14CRUSHED MISCELLANEOUS BASE692.00CY 642.70 642.700.00$35.00$0.00
15TRENCH BACKFILL SLURRY (CLASS 270-E-500)3.00CY 0.00 0.000.00$150.00$0.00
16CEMENT STABILIZED PULVERIZED BASE, 8" THICK83,518.00SY 82,961.00 82,961.000.00$4.50$0.00
17PORTLAND CEMENT FOR CSPB1,627.00TON 1,735.85 1,735.850.00$140.00$0.00
18PRIME/TACK COAT FOR CSPB12,522.00GAL 9,000.00 9,000.000.00$3.50$0.00
19COLD MILL AC PAVEMENT (0 - 1-1/2")123,365.00SF 95,328.00 95,328.000.00$0.15$0.00
20COLD MILL AC PAVEMENT (> 1-1/2 - 3")681,866.00SF 681,866.00 681,866.000.00$0.25$0.00
21AC PAVEMENT(PATCH BACK)3.00TON 3.00 3.000.00$500.00$0.00
22RECONSTRUCT MANHOLE73.00EA 72.00 72.000.00$800.00$0.00
23DOUBLE ADJUST MANHOLE6.00EA 5.00 5.000.00$500.00$0.00
24ASPHALT RUBBER HOT MIX6,610.00TON 6,858.00 6,858.000.00$78.00$0.00
25ASPHALT RUBBER HOT MIX (TEST STRIP)500.00TON 500.00 500.000.00$90.00$0.00
26COLD CENTRAL PLANT RECYCLED ASPHALT CONCRETE PAVEMENT (CCPRACP), 3" THICK83,518.00SY 82,961.00 82,961.000.00$6.00$0.00
27IMPORT RECLAIMED ASPHALT PAVEMENT (RAP)3,400.00TON 2,200.00 2,200.000.00$10.00$0.00
28EMULSIFIED RECYCLING AGENT450.00TON 426.09 426.090.00$700.00$0.00
29CONCRETE SLOUGH WALL4.00CY 3.51 3.510.00$1,000.00$0.00
30PCC CURB & GUTTER, TYPE A2-661.00LF 53.00 53.000.00$27.00$0.00
31PCC CURB & GUTTER, TYPE A2-84,654.00LF 3,078.30 3,078.300.00$28.00$0.00
32PCC CURB & GUTTER, TYPE A2-VAR408.00LF 391.00 391.000.00$28.00$0.00
33PCC WALK & DRIVEWAYS, 4" THICK9,332.00SF 9,300.00 9,300.000.00$4.00$0.00
34PCC CURB RAMPS28.00CY 68.00 68.000.00$600.00$0.00
35DETECTABLE WARNING SURFACE560.00SF 444.00 444.000.00$20.00$0.00
36CROSS GUTTER365.00CY 365.00 365.000.00$600.00$0.00
37RIVER ROCK PAVING, 6" THICK19,031.00SF 16,575.00 16,575.000.00$6.50$0.00
38PERVIOUS CONCRETE, 6" THICK29,976.00SF 27,170.00 27,170.000.00$5.00$0.00
39NO. 3 CONCRETE AGGREGATE555.00CY 503.15 503.150.00$85.00$0.00
40METAL HAND RAILINGS PER STD PLAN 60669.00LF 69.00 69.000.00$100.00$0.00
41INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT1,500.00LF 932.00 932.000.00$7.00$0.00
42INSTALL FIRE HYDRANT LOCATION RPM10.00EA 37.00 37.000.00$25.00$0.00
43TRAFFIC CONTROL1.00LS 1.00 1.000.00$260,000.00$0.00
44FLASHING ARROW SIGN2.00EA 2.00 2.000.00$4,000.00$0.00
45LID-A, BIO-SWALE38.00EA 38.00 38.000.00$400.00$0.00
46LID-B, INFILTRATION UNIT2.00EA 2.00 2.000.00$1,600.00$0.00
47AGRONOMIC SOIL REPORTS5.00EA 5.00 5.000.00$1,300.00$0.00
48LANDSCAPING1.00LS 1.00 1.000.00$58,000.00$0.00
49IRRIGATION SYSTEM1.00LS 1.00 1.000.00$140,000.00$0.00
50PLANT ESTABLISHMENT PERIOD1.00LS 1.00 1.000.00$16,000.00$0.00
S-1REVISED MOVE-IN PERIOD WD 25.00 25.000.00$0.00$0.00
S-2INSTALLATION OF 135 ADDITIONAL SHRUBS LS 1.00 1.000.00$1,225.00$0.00
S-3SUPPLY AND INSTALL 134 TONS OF 2-INCH MINUS ROCK  LS 21,036.00 21,036.000.00$1.00$0.00
S-04ADDITIONAL WORKING DAYS  WD 0.00 0.000.00$0.00$0.00
S-05SEWER SPILL REIMBURSEMENT  LS 1.00 1.000.00($2,285.00)$0.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 0.00 0.000.00$100.00 $0.00
LIQUIDATED DAMAGESDAY 0.00 0.000.00$2,000.00 $0.00
LABOR COMPLIANCEVIOLATION 0.00 0.000.00$25.00 $0.00
AFFIRMATIVE ACTIONVIOLATION 0.00 0.000.00$200.00 $0.00
BEST MANAGEMENT PRACTICEVIOLATION 1.00 1.000.00$1,000.00 $0.00
SCHEDULE UPDATEMONTHLY 0.00 0.000.00$250.00 $0.00
LTWHP-MANDATORY GOALMTH 0.00 1.00-1.00$1,000.00 ($1,000.00)

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,483,298.16 $4,483,298.16 $0.00
Retained $224,164.93 $224,164.93 $0.00
Deducted $1,000.00 $2,000.00 ($1,000.00)
Due $4,258,133.23 $4,257,133.23 $1,000.00



*The term "As-Built" used by the Department of Public Works in combination with the Engineer's Monthly Estimate process indicates that the project has been field accepted and that the pay quantities and deductions as detailed above are FINAL. Unless a certified letter is received by this office within 14 calendar days disputing the amounts shown, an acceptance letter will be filed with the Board of Supervisors authorizing the release of retention.