Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
4 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.30
| 0.00 | 0.30 | $162,600.00 | $48,780.00 |
6 | MOBILIZATION | 1.00 | LS |
0.95
| 0.00 | 0.95 | $317,184.54 | $301,325.31 |
7 | CLEARING AND GRUBBING | 1.00 | LS |
0.50
| 0.00 | 0.50 | $42,000.00 | $21,000.00 |
9 | UNCLASSIFIED EXCAVATION | 940.00 | CY |
500.00
| 0.00 | 500.00 | $150.00 | $75,000.00 |
17 | AC PAVEMENT | 1,066.00 | TON |
956.00
| 0.00 | 956.00 | $100.00 | $95,600.00 |
20 | AC PAVEMENT(DIGOUTS) | 42.00 | TON |
42.00
| 0.00 | 42.00 | $135.00 | $5,670.00 |
24 | ASPHALT RUBBER HOT MIX (TEST STRIP) | 500.00 | TON |
450.00
| 0.00 | 450.00 | $112.00 | $50,400.00 |
26 | CIR AC PAVEMENT, 3" THICK | 116,830.00 | SY |
56,773.00
| 0.00 | 56,773.00 | $8.00 | $454,184.00 |
27 | EMULSIFIED RECYCLING AGENT | 698.00 | TON |
273.00
| 0.00 | 273.00 | $650.00 | $177,450.00 |
28 | CIRACP MIX DESIGN (STIPULATED UNIT PRICE OF $10,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
43 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.00 | 0.30 | $193,000.00 | $57,900.00 |
44 | FLASHING ARROW SIGN | 1.00 | EA |
1.00
| 0.00 | 1.00 | $1,150.00 | $1,150.00 |
S-1 | EXTEND NTP1 PERIOD 18 WD | | LS |
1.00
| 0.00 | 1.00 | $0.00 | $0.00 |