Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.85 | 0.05 | $162,600.00 | $8,130.00 |
7 | CLEARING AND GRUBBING | 1.00 | LS |
0.95
| 0.90 | 0.05 | $42,000.00 | $2,100.00 |
9 | UNCLASSIFIED EXCAVATION | 940.00 | CY |
935.00
| 565.00 | 370.00 | $150.00 | $55,500.00 |
10 | SHOULDER GRADING | 3.00 | MI |
3.00
| 0.00 | 3.00 | $4,300.00 | $12,900.00 |
11 | IMPORTED BORROW | 505.00 | CY |
500.00
| 0.00 | 500.00 | $80.00 | $40,000.00 |
12 | CRUSHED MISCELLANEOUS BASE | 46.00 | CY |
45.00
| 0.00 | 45.00 | $88.00 | $3,960.00 |
19 | AC PAVEMENT(INVERTED SHOULDERS) | 534.00 | TON |
382.00
| 0.00 | 382.00 | $143.00 | $54,626.00 |
29 | REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) | 2,565.00 | LF |
860.00
| 0.00 | 860.00 | $15.00 | $12,900.00 |
31 | ADJUST GUARDRAIL | 3,208.00 | LF |
960.00
| 0.00 | 960.00 | $9.50 | $9,120.00 |
33 | METAL BEAM GUARD RAILING (STEEL POST W/ PLASTIC BLOCK) | 414.00 | LF |
125.00
| 0.00 | 125.00 | $63.00 | $7,875.00 |
35 | FLARED TERMINAL SYSTEM (TYPE X-TENSION- W/ STEEL POSTS) | 3.00 | EA |
2.00
| 0.00 | 2.00 | $7,000.00 | $14,000.00 |
36 | IN-LINE TERMINAL SYSTEM (TYPE X-TENSION - W/ STEEL POST) | 51.00 | EA |
18.00
| 0.00 | 18.00 | $7,000.00 | $126,000.00 |
42 | INSTALL FIRE HYDRANT LOCATION RPM | 25.00 | EA |
25.00
| 0.00 | 25.00 | $61.00 | $1,525.00 |
43 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.85 | 0.05 | $193,000.00 | $9,650.00 |