Progress Payment 4
Project Name: Mulholland Highway and Stokes Canyon Road, et al.
Contractor: Sully-Miller Contracting Company
135 South State College Boulevard, Suite 400
Brea, CA 92821
Project ID: RDC0015701
Federal Number(s): None
Original Contract: $4,970,000.00
Awarded: 3/6/2018
Period Ending: 11/30/2018
Board Accepted: 4/16/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
7CLEARING AND GRUBBING1.00LS 1.00 0.950.05$42,000.00$2,100.00
29REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS)2,565.00LF 2,065.00 860.001,205.00$15.00$18,075.00
31ADJUST GUARDRAIL3,208.00LF 2,437.00 960.001,477.00$9.50$14,031.50
32ADJUST GUARDRAIL AT BURIED END POST4.00EA 2.00 0.002.00$900.00$1,800.00
33METAL BEAM GUARD RAILING (STEEL POST W/ PLASTIC BLOCK)414.00LF 362.00 125.00237.00$63.00$14,931.00
34MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK)620.00LF 556.00 0.00556.00$61.00$33,916.00
35FLARED TERMINAL SYSTEM (TYPE X-TENSION- W/ STEEL POSTS)3.00EA 3.00 2.001.00$7,000.00$7,000.00
36IN-LINE TERMINAL SYSTEM (TYPE X-TENSION - W/ STEEL POST)51.00EA 39.00 18.0021.00$7,000.00$147,000.00
38MIDWEST GUARDRAIL SYSTEM END ANCHOR ASSEMBLY (TYPE SFT) PER STD PLAN A77S11.00EA 1.00 0.001.00$1,175.00$1,175.00
39MIDWEST GUARDRAIL SYSTEM BURIED POST END ANCHOR PER STD PLAN A77T21.00EA 1.00 0.001.00$6,000.00$6,000.00
43TRAFFIC CONTROL1.00LS 0.95 0.900.05$193,000.00$9,650.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
MONTHLY LOCAL HIRE PARTICIPATION CONTRACT COMPLIANCE VALUEEA 4.00 3.001.00$1,000.00 $1,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,536,479.50 $4,280,801.00 $255,678.50
Retained $226,823.98 $214,040.05 $12,783.93
Deducted $4,000.00 $3,000.00 $1,000.00
Due $4,305,655.52 $4,063,760.95 $241,894.57