Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 0.90 | 0.10 | $162,600.00 | $16,260.00 |
9 | UNCLASSIFIED EXCAVATION | 940.00 | CY |
940.00
| 935.00 | 5.00 | $150.00 | $750.00 |
11 | IMPORTED BORROW | 505.00 | CY |
505.00
| 500.00 | 5.00 | $80.00 | $400.00 |
24 | ASPHALT RUBBER HOT MIX (TEST STRIP) | 500.00 | TON |
500.00
| 489.00 | 11.00 | $112.00 | $1,232.00 |
29 | REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) | 2,565.00 | LF |
2,228.00
| 2,065.00 | 163.00 | $15.00 | $2,445.00 |
31 | ADJUST GUARDRAIL | 3,208.00 | LF |
2,545.00
| 2,437.00 | 108.00 | $9.50 | $1,026.00 |
33 | METAL BEAM GUARD RAILING (STEEL POST W/ PLASTIC BLOCK) | 414.00 | LF |
376.00
| 362.00 | 14.00 | $63.00 | $882.00 |
34 | MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) | 620.00 | LF |
570.00
| 556.00 | 14.00 | $61.00 | $854.00 |
36 | IN-LINE TERMINAL SYSTEM (TYPE X-TENSION - W/ STEEL POST) | 51.00 | EA |
43.00
| 39.00 | 4.00 | $7,000.00 | $28,000.00 |
37 | IN-LINE TERMINAL SYSTEM (TYPE SKT-SP-MGS) | 4.00 | EA |
4.00
| 0.00 | 4.00 | $5,300.00 | $21,200.00 |
43 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.95 | 0.05 | $193,000.00 | $9,650.00 |