Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $2,000.00 | $0.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
3.00
| 3.00 | 0.00 | $500.00 | $0.00 |
3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
4 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 1.00 | 0.00 | $162,600.00 | $0.00 |
6 | MOBILIZATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $317,184.54 | $0.00 |
7 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 1.00 | 0.00 | $42,000.00 | $0.00 |
8 | CONCRETE REMOVAL (NON-REINFORCED) | 2.00 | CY |
4.68
| 4.68 | 0.00 | $850.00 | $0.00 |
9 | UNCLASSIFIED EXCAVATION | 940.00 | CY |
940.46
| 940.00 | 0.46 | $150.00 | $69.00 |
10 | SHOULDER GRADING | 3.00 | MI |
3.00
| 3.00 | 0.00 | $4,300.00 | $0.00 |
11 | IMPORTED BORROW | 505.00 | CY |
521.00
| 521.00 | 0.00 | $80.00 | $0.00 |
12 | CRUSHED MISCELLANEOUS BASE | 46.00 | CY |
45.00
| 45.00 | 0.00 | $88.00 | $0.00 |
13 | COLD MILL AC PAVEMENT (0 - 1-1/2") | 7,805.00 | SF |
8,689.00
| 8,689.00 | 0.00 | $1.60 | $0.00 |
14 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 241,863.00 | SF |
243,380.00
| 243,380.00 | 0.00 | $0.42 | $0.00 |
15 | AC DIKE, TYPE A PER CALTRANS STD PLAN A87B | 40.00 | LF |
20.00
| 20.00 | 0.00 | $8.00 | $0.00 |
16 | AC DIKE, TYPE C PER CALTRANS STD PLAN A87B | 433.00 | LF |
360.00
| 360.00 | 0.00 | $6.00 | $0.00 |
17 | AC PAVEMENT | 1,066.00 | TON |
1,066.00
| 1,066.00 | 0.00 | $100.00 | $0.00 |
18 | AC PAVEMENT(DRIVEWAYS) | 137.00 | TON |
151.85
| 151.85 | 0.00 | $187.00 | $0.00 |
19 | AC PAVEMENT(INVERTED SHOULDERS) | 534.00 | TON |
382.00
| 382.00 | 0.00 | $143.00 | $0.00 |
20 | AC PAVEMENT(DIGOUTS) | 42.00 | TON |
42.00
| 42.00 | 0.00 | $135.00 | $0.00 |
21 | AC DIKE, TYPE F PER CALTRANS STD PLAN A87B | 446.00 | LF |
426.00
| 426.00 | 0.00 | $7.00 | $0.00 |
22 | DOUBLE ADJUST MANHOLE | 12.00 | EA |
13.00
| 13.00 | 0.00 | $1,100.00 | $0.00 |
23 | ASPHALT RUBBER HOT MIX | 14,201.00 | TON |
12,841.00
| 12,841.00 | 0.00 | $105.00 | $0.00 |
24 | ASPHALT RUBBER HOT MIX (TEST STRIP) | 500.00 | TON |
500.00
| 500.00 | 0.00 | $112.00 | $0.00 |
25 | ASPHALT RUBBER AND AGGREGATE MEMBRANE | 26,333.00 | SY |
26,868.00
| 26,868.00 | 0.00 | $6.00 | $0.00 |
26 | CIR AC PAVEMENT, 3" THICK | 116,830.00 | SY |
119,628.61
| 119,628.61 | 0.00 | $8.00 | $0.00 |
27 | EMULSIFIED RECYCLING AGENT | 698.00 | TON |
584.15
| 584.15 | 0.00 | $650.00 | $0.00 |
28 | CIRACP MIX DESIGN (STIPULATED UNIT PRICE OF $10,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $10,000.00 | $0.00 |
29 | REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) | 2,565.00 | LF |
2,465.00
| 2,465.00 | 0.00 | $15.00 | $0.00 |
30 | TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE | 42,640.00 | LB |
26,560.00
| 26,560.00 | 0.00 | $0.25 | $0.00 |
31 | ADJUST GUARDRAIL | 3,208.00 | LF |
2,883.00
| 2,883.00 | 0.00 | $9.50 | $0.00 |
32 | ADJUST GUARDRAIL AT BURIED END POST | 4.00 | EA |
2.00
| 2.00 | 0.00 | $900.00 | $0.00 |
33 | METAL BEAM GUARD RAILING (STEEL POST W/ PLASTIC BLOCK) | 414.00 | LF |
389.00
| 389.00 | 0.00 | $63.00 | $0.00 |
34 | MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) | 620.00 | LF |
620.00
| 620.00 | 0.00 | $61.00 | $0.00 |
35 | FLARED TERMINAL SYSTEM (TYPE X-TENSION- W/ STEEL POSTS) | 3.00 | EA |
3.00
| 3.00 | 0.00 | $7,000.00 | $0.00 |
36 | IN-LINE TERMINAL SYSTEM (TYPE X-TENSION - W/ STEEL POST) | 51.00 | EA |
48.00
| 48.00 | 0.00 | $7,000.00 | $0.00 |
37 | IN-LINE TERMINAL SYSTEM (TYPE SKT-SP-MGS) | 4.00 | EA |
4.00
| 4.00 | 0.00 | $5,300.00 | $0.00 |
38 | MIDWEST GUARDRAIL SYSTEM END ANCHOR ASSEMBLY (TYPE SFT) PER STD PLAN A77S1 | 1.00 | EA |
1.00
| 1.00 | 0.00 | $1,175.00 | $0.00 |
39 | MIDWEST GUARDRAIL SYSTEM BURIED POST END ANCHOR PER STD PLAN A77T2 | 1.00 | EA |
1.00
| 1.00 | 0.00 | $6,000.00 | $0.00 |
40 | TRANSITION RAILING (TYPE WB) | 4.00 | EA |
3.00
| 3.00 | 0.00 | $4,950.00 | $0.00 |
41 | ANCHOR BLOCK FOR TRANSITION RAILING CONNECTION PER STD PLAN A77U3 | 4.00 | EA |
4.00
| 4.00 | 0.00 | $3,425.00 | $0.00 |
42 | INSTALL FIRE HYDRANT LOCATION RPM | 25.00 | EA |
25.00
| 25.00 | 0.00 | $61.00 | $0.00 |
43 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 1.00 | 0.00 | $193,000.00 | $0.00 |
44 | FLASHING ARROW SIGN | 1.00 | EA |
1.00
| 1.00 | 0.00 | $1,150.00 | $0.00 |
45 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
2.00
| 2.00 | 0.00 | $2,500.00 | $0.00 |
S-1 | EXTEND NTP1 PERIOD 18 WD | | LS |
1.00
| 1.00 | 0.00 | $0.00 | $0.00 |
S-2 | REPAIR FIRE-DAMAGED GUARDRAILS (ADDENDUM V2.1) | | LS |
1.00
| 1.00 | 0.00 | $176,125.75 | $0.00 |
S-3 | PROCURE MATERIALS (ADDENDUM V2.1) | | LS |
1.00
| 1.00 | 0.00 | $105,174.25 | $0.00 |
S-4 | POTHOLE BURIED TELEPHONE CABLES (STA. 48+20 TO STA. 49+75) | | LS |
1.00
| 1.00 | 0.00 | $4,072.00 | $0.00 |
S-5 | REMOVE & DISPOSE OF 6 CONCRETE ANCHOR FOOTINGS | | LS |
1.00
| 1.00 | 0.00 | $6,519.00 | $0.00 |
S-6 | REIMBURSEMENT FOR CALTRANS PERMIT FEES | | T&M |
1,148.00
| 1,148.00 | 0.00 | $1.00 | $0.00 |
S-7 | RELOCATE SPRINKLER SYSTEM @ GUARDRAIL DETAIL "G5" | | LS |
1.00
| 1.00 | 0.00 | $1,138.00 | $0.00 |
S-8 | PROCURED/DELIVERED GUARDRAIL MATERIALS | | T&M |
22,258.95
| 22,258.95 | 0.00 | $1.00 | $0.00 |
S-9 | REMOVE & RE-INSTALL CHAIN LINK FENCE | | LS |
1.00
| 1.00 | 0.00 | $8,640.00 | $0.00 |
S-10 | POTHOLE AT&T ON MULHOLLAND HWY AT MM 0.8 & MM 6.71 | | T&M |
9,310.39
| 9,310.39 | 0.00 | $1.00 | $0.00 |
S-11 | INSTALL DELINEATORS (STD PLAN A77N4) | | LS |
1.00
| 1.00 | 0.00 | $4,160.00 | $0.00 |
S-12 | NONWORKING DAYS | | WD |
0.00
| 0.00 | 0.00 | $0.00 | $0.00 |