Los Angeles County Public Works
Project Management Division III
Release of Retention 13
Project Name: Mulholland Highway and Stokes Canyon Road, et al.
Contractor: Sully-Miller Contracting Company
135 South State College Boulevard, Suite 400
Brea, CA 92821
Project ID: RDC0015701
Federal Number(s): None
Original Contract: $4,970,000.00
Awarded: 3/6/2018
Period Ending: 4/20/2020
Board Accepted: 4/16/2020
There is NO item progress this period

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,066,403.72 $5,066,403.72 $0.00
Retained $0.00 $126,660.12 ($126,660.12)
Deducted $0.00 $0.00 $0.00
Due $5,066,403.72 $4,939,743.60 $126,660.12



Contact Office Engineer
Contractor Copy  