Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: Huntington Drive - San Gabriel Bl/132' West of Michillinda Avenue
Contractor: Sequel Contractors, Inc.
13546 Imperial Highway
Santa Fe Springs, CA 90670
Project ID: RDC0015735
Federal Number(s): None
Original Contract: $4,745,494.75
Awarded: 8/3/2021
Period Ending: 8/6/2022
Board Accepted: 2/13/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)12.00MTH 4.00 3.001.00$500.00$500.00
7IMPLEMENTATION OF THE SWPPP1.00LS 0.60 0.500.10$20,000.00$2,000.00
9OFFICE FACILITIES13.00MTH 5.00 4.001.00$2,500.00$2,500.00
11CLEARING AND GRUBBING1.00LS 0.95 0.900.05$90,000.00$4,500.00
14UNCLASSIFIED EXCAVATION1,903.00CY 1,037.64 762.96274.68$98.00$26,918.64
16CRUSHED MISCELLANEOUS BASE2,063.00CY 121.38 51.3870.00$20.00$1,400.00
17TRENCH BACKFILL SLURRY (CLASS 100-E-100)85.00CY 41.00 31.0010.00$400.00$4,000.00
19COLD MILL AC PAVEMENT (> 3")713,350.00SF 206,551.00 100,460.00106,091.00$0.67$71,080.97
21AC PAVEMENT11,384.00TON 3,499.08 1,694.021,805.06$71.00$128,159.26
39PCC CURB & GUTTER, TYPE A2-61,802.00LF 1,886.00 1,747.00139.00$38.00$5,282.00
44PCC WALK, 4" THICK2,498.00SF 3,114.46 1,944.461,170.00$15.00$17,550.00
45PCC CURB RAMPS40.00CY 13.69 12.211.48$1,400.00$2,072.00
72TYPE III-B SERVICE CABINET FOUNDATION1.00EA 1.00 0.001.00$1,500.00$1,500.00
116TRAFFIC CONTROL1.00LS 0.60 0.500.10$200,000.00$20,000.00
118CHANGEABLE MESSAGE SIGN2.00EA 1.30 1.200.10$40,000.00$4,000.00
122IRRIGATION SYSTEM1.00LS 0.75 0.500.25$95,000.00$23,750.00
S-08 REMOVE OLD IRRIGATION SYSTEM LS 0.20 0.000.20$15,000.00$3,000.00
S-10UPGRADE IRRIGATION SYSTEM LS 0.40 0.000.40$132,562.50$53,025.00
S-12REMOVAL OF 9 TREES LS 1.00 0.001.00$16,400.00$16,400.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,597,547.07 $1,209,909.20 $387,637.87
Retained $79,877.37 $60,495.47 $19,381.90
Deducted $0.00 $0.00 $0.00
Due $1,517,669.70 $1,149,413.73 $368,255.97