Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.70
| 0.60 | 0.10 | $20,000.00 | $2,000.00 |
9 | OFFICE FACILITIES | 13.00 | MTH |
6.00
| 5.00 | 1.00 | $2,500.00 | $2,500.00 |
11 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.95 | 0.05 | $90,000.00 | $4,500.00 |
14 | UNCLASSIFIED EXCAVATION | 1,903.00 | CY |
1,556.36
| 1,037.64 | 518.72 | $98.00 | $50,834.56 |
116 | TRAFFIC CONTROL | 1.00 | LS |
0.70
| 0.60 | 0.10 | $200,000.00 | $20,000.00 |
118 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
1.40
| 1.30 | 0.10 | $40,000.00 | $4,000.00 |
127 | ALUMINUM EDGING | 9,661.00 | LF |
534.00
| 0.00 | 534.00 | $10.00 | $5,340.00 |
S-07 | GROUTED RIVER ROCK PAVING | | SF |
2,045.00
| 0.00 | 2,045.00 | $12.99 | $26,564.55 |
S-08 | REMOVE OLD IRRIGATION SYSTEM | | LS |
0.30
| 0.20 | 0.10 | $15,000.00 | $1,500.00 |
S-10 | UPGRADE IRRIGATION SYSTEM | | LS |
0.50
| 0.40 | 0.10 | $132,562.50 | $13,256.25 |