Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 12.00 | MTH |
8.00
| 7.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.75
| 0.00 | 0.75 | $25,000.00 | $18,750.00 |
7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 0.95 | 0.05 | $20,000.00 | $1,000.00 |
9 | OFFICE FACILITIES | 13.00 | MTH |
11.00
| 10.00 | 1.00 | $2,500.00 | $2,500.00 |
12 | CONCRETE REMOVAL (NON-REINFORCED) | 395.00 | CY |
384.90
| 310.41 | 74.49 | $160.00 | $11,918.40 |
14 | UNCLASSIFIED EXCAVATION | 1,903.00 | CY |
1,918.00
| 1,871.41 | 46.59 | $98.00 | $4,565.82 |
16 | CRUSHED MISCELLANEOUS BASE | 2,063.00 | CY |
557.14
| 225.43 | 331.71 | $20.00 | $6,634.20 |
19 | COLD MILL AC PAVEMENT (> 3") | 713,350.00 | SF |
545,697.00
| 376,551.00 | 169,146.00 | $0.67 | $113,327.82 |
116 | TRAFFIC CONTROL | 1.00 | LS |
0.95
| 0.93 | 0.02 | $200,000.00 | $4,000.00 |
117 | FLASHING ARROW SIGN | 3.00 | EA |
2.75
| 2.55 | 0.20 | $20,000.00 | $4,000.00 |
118 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
1.85
| 1.75 | 0.10 | $40,000.00 | $4,000.00 |