Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 12.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
6 | OFFICE FACILITIES | 12.00 | MTH |
3.00
| 2.00 | 1.00 | $4,200.00 | $4,200.00 |
7 | MOBILIZATION | 1.00 | LS |
0.75
| 0.50 | 0.25 | $361,451.60 | $90,362.90 |
12 | CHANGEABLE MESSAGE SIGN | 8.00 | EA |
3.00
| 2.00 | 1.00 | $13,000.00 | $13,000.00 |
13 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 4.00 | EA |
0.00
| 4.00 | -4.00 | $1,700.00 | ($6,800.00) |
19 | CONCRETE REMOVAL (NON-REINFORCED) | 1,724.00 | CY |
65.38
| 32.00 | 33.38 | $166.00 | $5,541.08 |
20 | CONCRETE REMOVAL (REINFORCED) | 180.00 | CY |
166.55
| 149.00 | 17.55 | $210.00 | $3,685.50 |
21 | UNCLASSIFIED EXCAVATION | 1,848.00 | CY |
376.00
| 328.00 | 48.00 | $105.00 | $5,040.00 |
23 | STRUCTURE EXCAVATION | 81.00 | CY |
12.03
| 46.00 | -33.97 | $88.00 | ($2,989.36) |
49 | CURB DRAIN PER STD PLAN 150, N=1, CASE 3 INLET | 13.00 | EA |
1.00
| 0.00 | 1.00 | $300.00 | $300.00 |
55 | PCC CURB & GUTTER, TYPE A2-6 | 10,356.00 | LF |
460.60
| 208.00 | 252.60 | $28.00 | $7,072.80 |
61 | PCC CURB RAMPS | 94.00 | CY |
24.09
| 3.65 | 20.44 | $870.00 | $17,782.80 |
63 | CHANNEL SUPPORT SLAB (PER DETAILS ON SHEET 27) | 89.00 | CY |
89.00
| 73.00 | 16.00 | $1,900.00 | $30,400.00 |
66 | DETECTABLE WARNING SURFACE | 915.00 | SF |
270.00
| 60.00 | 210.00 | $41.00 | $8,610.00 |
67 | CROSS GUTTER | 82.00 | CY |
42.45
| 0.00 | 42.45 | $500.00 | $21,225.00 |
70 | REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) | 2,178.00 | LF |
2,177.00
| 624.50 | 1,552.50 | $11.00 | $17,077.50 |
72 | METAL BEAM GUARD RAILING (STEEL POST W/ PLASTIC BLOCK) | 13.00 | LF |
13.00
| 0.00 | 13.00 | $220.00 | $2,860.00 |
73 | MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) | 1,846.00 | LF |
1,800.00
| 922.50 | 877.50 | $40.00 | $35,100.00 |
74 | IN-LINE TERMINAL SYSTEM (TYPE MSKT-SP-MGS) | 29.00 | EA |
29.00
| 25.00 | 4.00 | $5,300.00 | $21,200.00 |
S-2 | 9 INCH CHANNEL SUPPORT SLAB (PER REVISED SHEET #27) | | LF |
44.54
| 0.00 | 44.54 | $1,500.00 | $66,810.00 |
S-3 | 9 INCH CHANNEL SUPPORT SLAB (PER REVISED SHEET #27) REMOVAL | | CY |
31.72
| 0.00 | 31.72 | $1,500.00 | $47,580.00 |