Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: McDonnell Avenue, et al.
Contractor: Sully-Miller Contracting Company
135 South State College Boulevard, Suite 400
Brea, CA 92821
Project ID: RDC0015818
Federal Number(s): None
Original Contract: $3,076,035.42
Awarded: 10/18/2016
Period Ending: 10/4/2017
Board Accepted: 12/21/2017
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
31RECONSTRUCT MANHOLE76.00EA 69.00 14.0055.00$1,500.00$82,500.00
53PCC WALK, DRIVES & CURB RAMPS, 4" THICK42,145.00SF 39,981.00 38,726.001,255.00$5.90$7,404.50
62FURNISH AND PLANT 15 GALLON TREE61.00EA 61.00 29.0032.00$300.00$9,600.00
63DECOMPOSED GRANITE, 4" THICK852.00SF 790.00 0.00790.00$6.00$4,740.00
64RIVER ROCK PAVING - GROUTED143.00SF 143.00 0.00143.00$18.00$2,574.00
65SOD759.00SY 722.00 0.00722.00$20.00$14,440.00
67RECONSTRUCT LOCAL DEPRESSION PER STD PLAN 313-3 CASE E11.00EA 11.00 10.001.00$385.00$385.00
76PAVEMENT MARKINGS (THERMOPLASTIC)1,544.00SF 1,544.00 1,384.00160.00$5.75$920.00
79INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT1,605.00LF 1,130.00 1,000.00130.00$11.00$1,430.00
80INSTALL FIRE HYDRANT LOCATION RPM33.00EA 33.00 26.007.00$5.50$38.50
81REMOVE VEHICLE HEAD (COMPLETE)7.00EA 7.00 0.007.00$143.00$1,001.00
823-12" LED VEHICLE HEAD (COMPLETE) 7.00EA 7.00 0.007.00$1,650.00$11,550.00
S-3STABILIZE PUMPING SUBGRADE T&M 0.00 66,000.00-66,000.00$1.00($66,000.00)
S-3ASTABILIZE PUMPING SUBGRADE LS 1.00 0.001.00$66,000.00$66,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,088,859.60 $2,952,276.60 $136,583.00
Retained $153,642.99 $146,813.84 $6,829.15
Deducted $0.00 $0.00 $0.00
Due $2,935,216.61 $2,805,462.76 $129,753.85



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.