Los Angeles County Public Works
Project Management Division III
Progress Payment 2
Project Name: Pathfinder Road
Contractor: Sequel Contractors, Inc.
13546 Imperial Highway
Santa Fe Springs, CA 90670
Project ID: RDC0015891
Federal Number(s): None
Original Contract: $372,069.75
Awarded: 2/2/2016
Period Ending: 7/27/2016
Board Accepted: 8/24/2016
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
5CLEARING AND GRUBBING1.00LS 1.00 0.900.10$5,200.00$520.00
6CONCRETE REMOVAL (NON-REINFORCED)93.00CY 97.74 93.004.74$130.00$616.20
7UNCLASSIFIED EXCAVATION302.00CY 278.02 157.19120.83$100.00$12,083.00
10PORTLAND CEMENT FOR CSPB142.00TON 138.51 128.2210.29$110.00$1,131.90
11PRIME/TACK COAT FOR CSPB503.00GAL 600.00 240.00360.00$6.00$2,160.00
12COLD MILL AC PAVEMENT (> 1-1/2 - 3")45,600.00SF 46,800.00 45,600.001,200.00$0.30$360.00
16DOUBLE ADJUST MANHOLE1.00EA 2.00 1.001.00$1,000.00$1,000.00
17ASPHALT RUBBER HOT MIX897.00TON 1,007.70 897.00110.70$83.00$9,188.10
20PCC WALK, 4" THICK4,833.00SF 5,968.00 4,833.001,135.00$4.00$4,540.00
23INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT475.00LF 457.00 0.00457.00$8.00$3,656.00
24REMOVE VEHICLE HEAD (COMPLETE)2.00EA 2.00 0.002.00$300.00$600.00
253-12" LED VEHICLE HEAD (COMPLETE) 1.00EA 1.00 0.001.00$1,500.00$1,500.00
264-12" LED VEHICLE HEAD (COMPLETE)1.00EA 1.00 0.001.00$2,000.00$2,000.00
27DETAIL 9 (THERMOPLASTIC)2,180.00LF 2,085.00 0.002,085.00$0.40$834.00
28DETAIL 22 (THERMOPLASTIC)600.00LF 600.00 0.00600.00$1.00$600.00
29DETAIL 29 (THERMOPLASTIC)475.00LF 630.00 0.00630.00$2.00$1,260.00
30DETAIL 32 (THERMOPLASTIC)85.00LF 97.00 0.0097.00$2.00$194.00
31DETAIL 38 (THERMOPLASTIC)720.00LF 720.00 0.00720.00$1.00$720.00
32DETAIL 39 (THERMOPLASTIC)1,405.00LF 1,742.00 0.001,742.00$0.75$1,306.50
33DETAIL 39A (THERMOPLASTIC)400.00LF 400.00 0.00400.00$0.50$200.00
34PAVEMENT MARKINGS (THERMOPLASTIC)276.00SF 318.00 0.00318.00$5.00$1,590.00
3512" STRIPING (THERMOPLASTIC)195.00LF 175.00 0.00175.00$3.00$525.00
38INSTALL SIGNS ON BARRICADES/POSTS35.00EA 35.00 20.0015.00$30.00$450.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $380,049.01 $333,014.31 $47,034.70
Retained $19,002.45 $16,650.71 $2,351.74
Deducted $0.00 $0.00 $0.00
Due $361,046.56 $316,363.60 $44,682.96



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.