Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
7.00
| 6.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.70
| 0.60 | 0.10 | $23,000.00 | $2,300.00 |
6 | OFFICE FACILITIES | 9.00 | MTH |
7.00
| 6.00 | 1.00 | $2,600.00 | $2,600.00 |
15 | CONCRETE REMOVAL (NON-REINFORCED) | 3,146.00 | CY |
1,766.67
| 1,664.01 | 102.66 | $200.00 | $20,532.00 |
17 | UNCLASSIFIED EXCAVATION | 4,651.00 | CY |
3,054.36
| 2,597.74 | 456.62 | $135.00 | $61,643.70 |
18 | CRUSHED MISCELLANEOUS BASE | 4,751.00 | CY |
2,648.87
| 2,246.89 | 401.98 | $120.00 | $48,237.60 |
23 | AC PAVEMENT(PATCH BACK) | 1,008.00 | TON |
307.17
| 205.80 | 101.37 | $200.00 | $20,274.00 |
39 | PCC CURB & GUTTER, TYPE A2-6 | 469.00 | LF |
73.35
| 20.50 | 52.85 | $47.00 | $2,483.95 |
41 | PCC CURB & GUTTER, TYPE A2-VAR | 3,744.00 | LF |
2,151.21
| 1,448.57 | 702.64 | $49.00 | $34,429.36 |
44 | PCC WALK, 4" THICK | 40,585.00 | SF |
29,488.27
| 24,365.21 | 5,123.06 | $10.00 | $51,230.60 |
45 | PCC CURB RAMPS | 461.00 | CY |
317.79
| 274.35 | 43.44 | $1,200.00 | $52,128.00 |
46 | PCC DRIVEWAYS, 6" THICK | 1,697.00 | SF |
1,697.00
| 1,647.55 | 49.45 | $13.00 | $642.85 |
47 | DETECTABLE WARNING SURFACE | 3,742.00 | SF |
1,835.43
| 1,540.43 | 295.00 | $40.00 | $11,800.00 |
55 | ADJUST PULL BOX | 113.00 | EA |
70.00
| 53.00 | 17.00 | $500.00 | $8,500.00 |
93 | TRAFFIC CONTROL | 1.00 | LS |
0.70
| 0.60 | 0.10 | $211,000.00 | $21,100.00 |
S-3 | TRAFFIC SIGNAL COMPONENTS | | T&M |
529,142.99
| 498,484.14 | 30,658.85 | $1.00 | $30,658.85 |
|