Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.30
| 0.00 | 0.30 | $6,000.00 | $1,800.00 |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.30
| 0.00 | 0.30 | $19,000.00 | $5,700.00 |
6 | OFFICE FACILITIES | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $3,600.00 | $3,600.00 |
7 | MOBILIZATION | 1.00 | LS |
0.30
| 0.00 | 0.30 | $178,000.00 | $53,400.00 |
8 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.00 | 1.00 | $4,000.00 | $4,000.00 |
9 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 33.00 | EA |
25.00
| 0.00 | 25.00 | $630.00 | $15,750.00 |
10 | TREE REMOVAL (6"-12" DIAMETER) | 1.00 | EA |
1.00
| 0.00 | 1.00 | $950.00 | $950.00 |
11 | TREE REMOVAL (13"-24" DIAMETER) | 5.00 | EA |
5.00
| 0.00 | 5.00 | $950.00 | $4,750.00 |
12 | CROWN REDUCTION, TREE (1" - 12" DIAMETER) | 6.00 | EA |
1.00
| 0.00 | 1.00 | $360.00 | $360.00 |
13 | CROWN REDUCTION, TREE (13" - 24" DIAMETER) | 24.00 | EA |
24.00
| 0.00 | 24.00 | $360.00 | $8,640.00 |
15 | CONCRETE REMOVAL (NON-REINFORCED) | 332.00 | CY |
132.43
| 0.00 | 132.43 | $320.00 | $42,377.60 |
16 | UNCLASSIFIED EXCAVATION | 779.00 | CY |
190.27
| 0.00 | 190.27 | $200.00 | $38,054.00 |
17 | CRUSHED MISCELLANEOUS BASE | 587.00 | CY |
190.27
| 0.00 | 190.27 | $210.00 | $39,956.70 |
21 | AC PAVEMENT(PATCH BACK) | 7.00 | TON |
1.00
| 0.00 | 1.00 | $300.00 | $300.00 |
25 | REMOVE AND RECONSTRUCT EXISTING CURB DRAIN PER STD PLAN 150, N=1 | 16.00 | EA |
8.00
| 0.00 | 8.00 | $500.00 | $4,000.00 |
26 | PCC CURB, TYPE A1-VAR | 440.00 | LF |
21.00
| 0.00 | 21.00 | $49.00 | $1,029.00 |
28 | PCC CURB & GUTTER, TYPE A2-VAR | 487.00 | LF |
264.50
| 0.00 | 264.50 | $65.00 | $17,192.50 |
31 | PCC WALK & DRIVEWAYS, 4" THICK | 12,041.00 | SF |
9,214.00
| 0.00 | 9,214.00 | $13.00 | $119,782.00 |
37 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.00 | 0.30 | $129,000.00 | $38,700.00 |