Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.90
| 0.60 | 0.30 | $6,000.00 | $1,800.00 |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.90
| 0.60 | 0.30 | $19,000.00 | $5,700.00 |
6 | OFFICE FACILITIES | 4.00 | MTH |
3.00
| 2.00 | 1.00 | $3,600.00 | $3,600.00 |
7 | MOBILIZATION | 1.00 | LS |
0.90
| 0.60 | 0.30 | $178,000.00 | $53,400.00 |
16 | UNCLASSIFIED EXCAVATION | 779.00 | CY |
685.53
| 656.15 | 29.38 | $200.00 | $5,876.00 |
19 | COLD MILL AC PAVEMENT (0 - 1-1/2") | 243,923.00 | SF |
243,923.00
| 0.00 | 243,923.00 | $0.35 | $85,373.05 |
20 | AC PAVEMENT | 105.00 | TON |
71.50
| 30.00 | 41.50 | $300.00 | $12,450.00 |
23 | DOUBLE ADJUST MANHOLE | 37.00 | EA |
37.00
| 0.00 | 37.00 | $980.00 | $36,260.00 |
24 | ASPHALT RUBBER HOT MIX | 2,289.00 | TON |
2,186.00
| 0.00 | 2,186.00 | $120.00 | $262,320.00 |
37 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.60 | 0.30 | $129,000.00 | $38,700.00 |
38 | FURNISH AND PLANT 24" BOX TREE | 79.00 | EA |
69.00
| 0.00 | 69.00 | $940.00 | $64,860.00 |