Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 0.90 | 0.10 | $6,000.00 | $600.00 |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $19,000.00 | $1,900.00 |
7 | MOBILIZATION | 1.00 | LS |
1.00
| 0.90 | 0.10 | $178,000.00 | $17,800.00 |
36 | INSTALL FIRE HYDRANT LOCATION RPM | 26.00 | EA |
14.00
| 0.00 | 14.00 | $110.00 | $1,540.00 |
37 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.90 | 0.10 | $129,000.00 | $12,900.00 |
39 | LANDSCAPING | 1.00 | LS |
1.00
| 0.00 | 1.00 | $6,000.00 | $6,000.00 |
40 | PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
0.30
| 0.00 | 0.30 | $12,000.00 | $3,600.00 |
41 | WATER TRUCK AND WATERING BAG REFILLING TREE ESTABLISHMENT | 1.00 | LS |
0.30
| 0.00 | 0.30 | $60,000.00 | $18,000.00 |