Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
3.00
| 0.00 | 3.00 | $500.00 | $1,500.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.15
| 0.10 | 0.05 | $16,000.00 | $800.00 |
7 | OFFICE FACILITIES | 24.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
8 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $75,000.00 | $37,500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.15
| 0.00 | 0.15 | $30,000.00 | $4,500.00 |
10 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 92.00 | EA |
8.00
| 0.00 | 8.00 | $1,275.00 | $10,200.00 |
14 | CONCRETE REMOVAL (NON-REINFORCED) | 3,119.00 | CY |
230.00
| 62.17 | 167.83 | $156.00 | $26,181.48 |
16 | UNCLASSIFIED EXCAVATION | 3,316.00 | CY |
375.00
| 131.34 | 243.66 | $138.00 | $33,625.08 |
17 | UNCLASSIFIED EXCAVATION (ROADWAY) | 28,831.00 | CY |
2,903.00
| 0.00 | 2,903.00 | $72.00 | $209,016.00 |
18 | CRUSHED MISCELLANEOUS BASE | 4,205.00 | CY |
1,458.00
| 107.00 | 1,351.00 | $105.00 | $141,855.00 |
20 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 88,314.00 | SY |
0.00
| 1.00 | -1.00 | $4.90 | ($4.90) |
27 | AC PAVEMENT (PATCH BACK) TEMP | 386.00 | TON |
91.61
| 16.42 | 75.19 | $315.00 | $23,684.85 |
29 | RECONSTRUCT MANHOLE | 155.00 | EA |
5.00
| 1.00 | 4.00 | $1,800.00 | $7,200.00 |
31 | PCC PAVEMENT | 1,281.00 | CY |
1,281.00
| 0.00 | 1,281.00 | $390.00 | $499,590.00 |
42 | PCC CURB & GUTTER, TYPE A2-6 | 9,226.00 | LF |
157.50
| 0.00 | 157.50 | $33.00 | $5,197.50 |
43 | PCC CURB & GUTTER, TYPE A2-8 | 16,059.00 | LF |
1,042.00
| 152.00 | 890.00 | $37.00 | $32,930.00 |
45 | PCC CURB & GUTTER, TYPE A3-6 | 106.00 | LF |
106.00
| 0.00 | 106.00 | $34.00 | $3,604.00 |
47 | LONGITUDINAL GUTTER | 342.00 | CY |
320.37
| 0.00 | 320.37 | $495.00 | $158,583.15 |
48 | PCC WALK & DRIVEWAYS, 4" THICK | 64,556.00 | SF |
9,870.00
| 3,069.00 | 6,801.00 | $6.35 | $43,186.35 |
49 | PCC CURB RAMPS | 252.00 | CY |
15.47
| 6.91 | 8.56 | $675.00 | $5,778.00 |
51 | DETECTABLE WARNING SURFACE | 2,277.00 | SF |
137.00
| 65.00 | 72.00 | $43.00 | $3,096.00 |
52 | CROSS GUTTER | 475.00 | CY |
28.09
| 24.40 | 3.69 | $370.00 | $1,365.30 |
54 | ALLEY INTERSECTION | 142.00 | CY |
26.92
| 0.00 | 26.92 | $370.00 | $9,960.40 |
55 | METAL HAND RAILINGS PER STD PLAN 606 | 213.00 | LF |
93.00
| 0.00 | 93.00 | $180.00 | $16,740.00 |
59 | TRAFFIC CONTROL | 1.00 | LS |
0.15
| 0.00 | 0.15 | $370,000.00 | $55,500.00 |
S-1 | TEST 20 SOIL SAMPLES | | LS |
1.00
| 0.00 | 1.00 | $26,000.00 | $26,000.00 |
|