Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
7.00
| 6.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.12
| 0.00 | 0.12 | $40,000.00 | $4,800.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.35
| 0.30 | 0.05 | $16,000.00 | $800.00 |
7 | OFFICE FACILITIES | 24.00 | MTH |
7.00
| 6.00 | 1.00 | $500.00 | $500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.35
| 0.30 | 0.05 | $30,000.00 | $1,500.00 |
10 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 92.00 | EA |
44.00
| 20.00 | 24.00 | $1,275.00 | $30,600.00 |
12 | STUMP REMOVAL ONLY (13"-24" DIAMETER) | 55.00 | EA |
29.00
| 16.00 | 13.00 | $375.00 | $4,875.00 |
13 | STUMP REMOVAL ONLY (25"+ DIAMETER) | 29.00 | EA |
24.00
| 23.00 | 1.00 | $500.00 | $500.00 |
14 | CONCRETE REMOVAL (NON-REINFORCED) | 3,119.00 | CY |
1,370.90
| 974.38 | 396.52 | $156.00 | $61,857.12 |
15 | CONCRETE REMOVAL (REINFORCED) | 3.00 | CY |
4.41
| 3.00 | 1.41 | $1,800.00 | $2,538.00 |
16 | UNCLASSIFIED EXCAVATION | 3,316.00 | CY |
2,709.29
| 1,870.87 | 838.42 | $138.00 | $115,701.96 |
18 | CRUSHED MISCELLANEOUS BASE | 4,205.00 | CY |
2,764.00
| 2,537.49 | 226.51 | $105.00 | $23,783.55 |
19 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 50.00 | CY |
12.95
| 1.50 | 11.45 | $177.00 | $2,026.65 |
26 | AC PAVEMENT(PATCH BACK) | 23.00 | TON |
22.87
| 9.74 | 13.13 | $315.00 | $4,135.95 |
31 | PCC PAVEMENT | 1,281.00 | CY |
1,340.00
| 1,281.00 | 59.00 | $390.00 | $23,010.00 |
36 | CATCH BASIN PER STD PLAN 300, W=3 | 2.00 | EA |
4.00
| 0.00 | 4.00 | $8,000.00 | $32,000.00 |
41 | PCC CURB, TYPE A1-VAR | 16.00 | LF |
19.00
| 16.00 | 3.00 | $23.00 | $69.00 |
42 | PCC CURB & GUTTER, TYPE A2-6 | 9,226.00 | LF |
6,974.00
| 6,451.00 | 523.00 | $33.00 | $17,259.00 |
43 | PCC CURB & GUTTER, TYPE A2-8 | 16,059.00 | LF |
5,355.00
| 3,658.00 | 1,697.00 | $37.00 | $62,789.00 |
46 | PCC CURB & GUTTER, TYPE A3-8 | 63.00 | LF |
78.00
| 63.00 | 15.00 | $34.00 | $510.00 |
48 | PCC WALK & DRIVEWAYS, 4" THICK | 64,556.00 | SF |
42,208.00
| 36,383.00 | 5,825.00 | $6.35 | $36,988.75 |
49 | PCC CURB RAMPS | 252.00 | CY |
85.20
| 81.81 | 3.39 | $675.00 | $2,288.25 |
51 | DETECTABLE WARNING SURFACE | 2,277.00 | SF |
740.00
| 660.00 | 80.00 | $43.00 | $3,440.00 |
54 | ALLEY INTERSECTION | 142.00 | CY |
103.10
| 93.15 | 9.95 | $370.00 | $3,681.50 |
55 | METAL HAND RAILINGS PER STD PLAN 606 | 213.00 | LF |
235.00
| 213.00 | 22.00 | $180.00 | $3,960.00 |
56 | 18" RCP, 1500 D | 102.00 | LF |
102.00
| 0.00 | 102.00 | $525.00 | $53,550.00 |
59 | TRAFFIC CONTROL | 1.00 | LS |
0.35
| 0.30 | 0.05 | $370,000.00 | $18,500.00 |
61 | SOD | 1,649.00 | SY |
27.00
| 0.00 | 27.00 | $69.00 | $1,863.00 |
63 | RIVER ROCK PAVING | 488.00 | SF |
493.00
| 488.00 | 5.00 | $32.00 | $160.00 |
|