Progress Payment 8
Project Name: South Whittier Los Nietos - Keith Drive, et al.
Contractor: R. J. Noble Company
P.O. Box 620
Orange, CA 92856
Project ID: RMD4408001
Federal Number(s): None
Original Contract: $11,848,831.05
Awarded: 9/24/2019
Period Ending: 10/23/2020
Board Accepted: 12/21/2021
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)24.00MTH 8.00 7.001.00$500.00$500.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.40 0.350.05$16,000.00$800.00
7OFFICE FACILITIES24.00MTH 8.00 7.001.00$500.00$500.00
9CLEARING AND GRUBBING1.00LS 0.40 0.350.05$30,000.00$1,500.00
11STUMP REMOVAL ONLY (6"-12" DIAMETER)1.00EA 1.00 0.001.00$210.00$210.00
12STUMP REMOVAL ONLY (13"-24" DIAMETER)55.00EA 35.00 29.006.00$375.00$2,250.00
14CONCRETE REMOVAL (NON-REINFORCED)3,119.00CY 1,700.41 1,370.90329.51$156.00$51,403.56
15CONCRETE REMOVAL (REINFORCED)3.00CY 10.73 4.416.32$1,800.00$11,376.00
16UNCLASSIFIED EXCAVATION3,316.00CY 3,157.95 2,709.29448.66$138.00$61,915.08
18CRUSHED MISCELLANEOUS BASE4,205.00CY 3,509.00 2,764.00745.00$105.00$78,225.00
27AC PAVEMENT (PATCH BACK) TEMP386.00TON 241.49 220.1821.31$315.00$6,712.65
37JUNCTION STRUCTURE PER STD PLAN 3332.00EA 2.00 0.002.00$2,600.00$5,200.00
42PCC CURB & GUTTER, TYPE A2-69,226.00LF 7,950.00 6,974.00976.00$33.00$32,208.00
43PCC CURB & GUTTER, TYPE A2-816,059.00LF 9,072.00 5,355.003,717.00$37.00$137,529.00
48PCC WALK & DRIVEWAYS, 4" THICK64,556.00SF 58,206.00 42,208.0015,998.00$6.35$101,587.30
49PCC CURB RAMPS252.00CY 141.59 85.2056.39$675.00$38,063.25
51DETECTABLE WARNING SURFACE2,277.00SF 1,234.00 740.00494.00$43.00$21,242.00
52CROSS GUTTER475.00CY 227.19 121.59105.60$370.00$39,072.00
54ALLEY INTERSECTION142.00CY 140.65 103.1037.55$370.00$13,893.50
59TRAFFIC CONTROL1.00LS 0.40 0.350.05$370,000.00$18,500.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 7,000.00 6,500.00500.00$1.00 $500.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,899,928.16 $3,277,240.82 $622,687.34
Retained $194,996.44 $163,862.06 $31,134.38
Deducted $7,000.00 $6,500.00 $500.00
Due $3,697,931.72 $3,106,878.76 $591,052.96