Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
9.00
| 8.00 | 1.00 | $500.00 | $500.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.45
| 0.40 | 0.05 | $16,000.00 | $800.00 |
7 | OFFICE FACILITIES | 24.00 | MTH |
9.00
| 8.00 | 1.00 | $500.00 | $500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.45
| 0.40 | 0.05 | $30,000.00 | $1,500.00 |
17 | UNCLASSIFIED EXCAVATION (ROADWAY) | 28,831.00 | CY |
4,665.00
| 2,903.00 | 1,762.00 | $72.00 | $126,864.00 |
18 | CRUSHED MISCELLANEOUS BASE | 4,205.00 | CY |
3,633.71
| 3,509.00 | 124.71 | $105.00 | $13,094.55 |
21 | CEMENT STABILIZED PULVERIZED BASE, 12" THICK | 71,639.00 | SY |
15,614.00
| 0.00 | 15,614.00 | $5.10 | $79,631.40 |
22 | PORTLAND CEMENT FOR CSPB | 4,598.00 | TON |
517.66
| 0.00 | 517.66 | $152.00 | $78,684.32 |
23 | PRIME/TACK COAT FOR CSPB | 32,009.00 | GAL |
2,732.00
| 0.00 | 2,732.00 | $0.45 | $1,229.40 |
25 | AC PAVEMENT | 22,669.00 | TON |
2,117.00
| 0.00 | 2,117.00 | $70.00 | $148,190.00 |
27 | AC PAVEMENT (PATCH BACK) TEMP | 386.00 | TON |
247.44
| 241.49 | 5.95 | $315.00 | $1,874.25 |
43 | PCC CURB & GUTTER, TYPE A2-8 | 16,059.00 | LF |
9,665.00
| 9,072.00 | 593.00 | $37.00 | $21,941.00 |
48 | PCC WALK & DRIVEWAYS, 4" THICK | 64,556.00 | SF |
61,174.00
| 58,206.00 | 2,968.00 | $6.35 | $18,846.80 |
49 | PCC CURB RAMPS | 252.00 | CY |
163.30
| 141.59 | 21.71 | $675.00 | $14,654.25 |
51 | DETECTABLE WARNING SURFACE | 2,277.00 | SF |
1,354.00
| 1,234.00 | 120.00 | $43.00 | $5,160.00 |
53 | CROSS GUTTER (MOD) | 53.00 | CY |
11.58
| 7.13 | 4.45 | $370.00 | $1,646.50 |
54 | ALLEY INTERSECTION | 142.00 | CY |
142.00
| 140.65 | 1.35 | $370.00 | $499.50 |
59 | TRAFFIC CONTROL | 1.00 | LS |
0.45
| 0.40 | 0.05 | $370,000.00 | $18,500.00 |
|