Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
11.00
| 10.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.50
| 0.40 | 0.10 | $40,000.00 | $4,000.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.55
| 0.50 | 0.05 | $16,000.00 | $800.00 |
7 | OFFICE FACILITIES | 24.00 | MTH |
11.00
| 10.00 | 1.00 | $500.00 | $500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.55
| 0.50 | 0.05 | $30,000.00 | $1,500.00 |
17 | UNCLASSIFIED EXCAVATION (ROADWAY) | 28,831.00 | CY |
12,513.00
| 7,926.00 | 4,587.00 | $72.00 | $330,264.00 |
20 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 88,314.00 | SY |
25,372.00
| 4,660.00 | 20,712.00 | $4.90 | $101,488.80 |
21 | CEMENT STABILIZED PULVERIZED BASE, 12" THICK | 71,639.00 | SY |
44,288.00
| 35,368.00 | 8,920.00 | $5.10 | $45,492.00 |
22 | PORTLAND CEMENT FOR CSPB | 4,598.00 | TON |
1,624.12
| 1,103.91 | 520.21 | $152.00 | $79,071.92 |
23 | PRIME/TACK COAT FOR CSPB | 32,009.00 | GAL |
10,838.00
| 6,341.00 | 4,497.00 | $0.45 | $2,023.65 |
25 | AC PAVEMENT | 22,669.00 | TON |
9,853.69
| 5,564.41 | 4,289.28 | $70.00 | $300,249.60 |
29 | RECONSTRUCT MANHOLE | 155.00 | EA |
8.00
| 6.00 | 2.00 | $1,800.00 | $3,600.00 |
59 | TRAFFIC CONTROL | 1.00 | LS |
0.55
| 0.50 | 0.05 | $370,000.00 | $18,500.00 |
62 | RED BRICK WITH MORTAR PER DETAIL A ON SHEET 15 | 41.00 | SF |
41.00
| 0.00 | 41.00 | $50.00 | $2,050.00 |
|