Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
12.00
| 11.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.60
| 0.50 | 0.10 | $40,000.00 | $4,000.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.60
| 0.55 | 0.05 | $16,000.00 | $800.00 |
7 | OFFICE FACILITIES | 24.00 | MTH |
12.00
| 11.00 | 1.00 | $500.00 | $500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.60
| 0.55 | 0.05 | $30,000.00 | $1,500.00 |
14 | CONCRETE REMOVAL (NON-REINFORCED) | 3,119.00 | CY |
1,843.13
| 1,700.41 | 142.72 | $156.00 | $22,264.32 |
16 | UNCLASSIFIED EXCAVATION | 3,316.00 | CY |
3,338.34
| 3,157.95 | 180.39 | $138.00 | $24,893.82 |
18 | CRUSHED MISCELLANEOUS BASE | 4,205.00 | CY |
3,751.50
| 3,633.71 | 117.79 | $105.00 | $12,367.95 |
27 | AC PAVEMENT (PATCH BACK) TEMP | 386.00 | TON |
253.63
| 247.44 | 6.19 | $315.00 | $1,949.85 |
32 | ASPHALT RUBBER HOT MIX | 13,531.00 | TON |
300.06
| 0.00 | 300.06 | $90.00 | $27,005.40 |
33 | ASPHALT RUBBER HOT MIX (TEST STRIP) | 500.00 | TON |
500.00
| 0.00 | 500.00 | $107.00 | $53,500.00 |
43 | PCC CURB & GUTTER, TYPE A2-8 | 16,059.00 | LF |
10,268.00
| 9,665.00 | 603.00 | $37.00 | $22,311.00 |
48 | PCC WALK & DRIVEWAYS, 4" THICK | 64,556.00 | SF |
64,202.43
| 61,174.00 | 3,028.43 | $6.35 | $19,230.53 |
49 | PCC CURB RAMPS | 252.00 | CY |
174.19
| 163.30 | 10.89 | $675.00 | $7,350.75 |
51 | DETECTABLE WARNING SURFACE | 2,277.00 | SF |
1,444.00
| 1,354.00 | 90.00 | $43.00 | $3,870.00 |
52 | CROSS GUTTER | 475.00 | CY |
255.55
| 227.19 | 28.36 | $370.00 | $10,493.20 |
59 | TRAFFIC CONTROL | 1.00 | LS |
0.60
| 0.55 | 0.05 | $370,000.00 | $18,500.00 |
|