Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
13.00
| 12.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.65
| 0.60 | 0.05 | $40,000.00 | $2,000.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.65
| 0.60 | 0.05 | $16,000.00 | $800.00 |
7 | OFFICE FACILITIES | 24.00 | MTH |
13.00
| 12.00 | 1.00 | $500.00 | $500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.65
| 0.60 | 0.05 | $30,000.00 | $1,500.00 |
10 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 92.00 | EA |
53.00
| 44.00 | 9.00 | $1,275.00 | $11,475.00 |
14 | CONCRETE REMOVAL (NON-REINFORCED) | 3,119.00 | CY |
2,037.73
| 1,843.13 | 194.60 | $156.00 | $30,357.60 |
16 | UNCLASSIFIED EXCAVATION | 3,316.00 | CY |
3,833.10
| 3,338.34 | 494.76 | $138.00 | $68,276.88 |
18 | CRUSHED MISCELLANEOUS BASE | 4,205.00 | CY |
4,080.70
| 3,751.50 | 329.20 | $105.00 | $34,566.00 |
27 | AC PAVEMENT (PATCH BACK) TEMP | 386.00 | TON |
260.85
| 253.63 | 7.22 | $315.00 | $2,274.30 |
32 | ASPHALT RUBBER HOT MIX | 13,531.00 | TON |
3,497.88
| 300.06 | 3,197.82 | $90.00 | $287,803.80 |
43 | PCC CURB & GUTTER, TYPE A2-8 | 16,059.00 | LF |
13,443.00
| 10,268.00 | 3,175.00 | $37.00 | $117,475.00 |
48 | PCC WALK & DRIVEWAYS, 4" THICK | 64,556.00 | SF |
70,971.93
| 64,202.43 | 6,769.50 | $6.35 | $42,986.33 |
49 | PCC CURB RAMPS | 252.00 | CY |
189.75
| 174.19 | 15.56 | $675.00 | $10,503.00 |
51 | DETECTABLE WARNING SURFACE | 2,277.00 | SF |
1,536.00
| 1,444.00 | 92.00 | $43.00 | $3,956.00 |
52 | CROSS GUTTER | 475.00 | CY |
305.00
| 255.55 | 49.45 | $370.00 | $18,296.50 |
59 | TRAFFIC CONTROL | 1.00 | LS |
0.65
| 0.60 | 0.05 | $370,000.00 | $18,500.00 |
|