Los Angeles County Public Works
Project Management Division III
Progress Payment 16
Project Name: South Whittier Los Nietos - Keith Drive, et al.
Contractor: R. J. Noble Company
P.O. Box 620
Orange, CA 92856
Project ID: RMD4408001
Federal Number(s): None
Original Contract: $11,848,831.05
Awarded: 9/24/2019
Period Ending: 6/25/2021
Board Accepted: 12/21/2021
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)24.00MTH 16.00 15.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.80 0.750.05$40,000.00$2,000.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.80 0.750.05$16,000.00$800.00
7OFFICE FACILITIES24.00MTH 16.00 15.001.00$500.00$500.00
9CLEARING AND GRUBBING1.00LS 0.80 0.750.05$30,000.00$1,500.00
14CONCRETE REMOVAL (NON-REINFORCED)3,119.00CY 2,691.04 2,655.2435.80$156.00$5,584.80
16UNCLASSIFIED EXCAVATION3,316.00CY 5,010.92 4,988.8222.10$138.00$3,049.80
17UNCLASSIFIED EXCAVATION (ROADWAY)28,831.00CY 19,297.00 12,513.006,784.00$72.00$488,448.00
18CRUSHED MISCELLANEOUS BASE4,205.00CY 5,036.54 5,014.4422.10$105.00$2,320.50
20CEMENT STABILIZED PULVERIZED BASE, 8" THICK88,314.00SY 51,249.00 25,372.0025,877.00$4.90$126,797.30
21CEMENT STABILIZED PULVERIZED BASE, 12" THICK71,639.00SY 59,699.00 44,288.0015,411.00$5.10$78,596.10
22PORTLAND CEMENT FOR CSPB4,598.00TON 2,364.32 1,624.12740.20$152.00$112,510.40
23PRIME/TACK COAT FOR CSPB32,009.00GAL 17,210.00 10,838.006,372.00$0.45$2,867.40
25AC PAVEMENT22,669.00TON 15,292.59 9,853.695,438.90$70.00$380,723.00
27AC PAVEMENT (PATCH BACK) TEMP386.00TON 386.00 363.6522.35$315.00$7,040.25
29RECONSTRUCT MANHOLE155.00EA 39.00 31.008.00$1,800.00$14,400.00
43PCC CURB & GUTTER, TYPE A2-816,059.00LF 21,097.50 21,030.5067.00$37.00$2,479.00
48PCC WALK & DRIVEWAYS, 4" THICK64,556.00SF 91,475.50 91,335.50140.00$6.35$889.00
49PCC CURB RAMPS252.00CY 229.55 252.00-22.45$675.00($15,153.75)
51DETECTABLE WARNING SURFACE2,277.00SF 1,827.00 1,782.0045.00$43.00$1,935.00
59TRAFFIC CONTROL1.00LS 0.80 0.700.10$370,000.00$37,000.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 15,000.00 14,000.001,000.00$1.00 $1,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $9,232,014.77 $7,977,227.97 $1,254,786.80
Retained $461,600.77 $398,861.42 $62,739.35
Deducted $15,000.00 $14,000.00 $1,000.00
Due $8,755,414.00 $7,564,366.55 $1,191,047.45