Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
17.00
| 16.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.85
| 0.80 | 0.05 | $40,000.00 | $2,000.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.85
| 0.80 | 0.05 | $16,000.00 | $800.00 |
7 | OFFICE FACILITIES | 24.00 | MTH |
17.00
| 16.00 | 1.00 | $500.00 | $500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.85
| 0.80 | 0.05 | $30,000.00 | $1,500.00 |
17 | UNCLASSIFIED EXCAVATION (ROADWAY) | 28,831.00 | CY |
28,631.00
| 19,297.00 | 9,334.00 | $72.00 | $672,048.00 |
20 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 88,314.00 | SY |
62,340.00
| 51,249.00 | 11,091.00 | $4.90 | $54,345.90 |
21 | CEMENT STABILIZED PULVERIZED BASE, 12" THICK | 71,639.00 | SY |
71,634.00
| 59,699.00 | 11,935.00 | $5.10 | $60,868.50 |
22 | PORTLAND CEMENT FOR CSPB | 4,598.00 | TON |
2,860.71
| 2,364.32 | 496.39 | $152.00 | $75,451.28 |
59 | TRAFFIC CONTROL | 1.00 | LS |
0.85
| 0.80 | 0.05 | $370,000.00 | $18,500.00 |