Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
18.00
| 17.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.90
| 0.85 | 0.05 | $40,000.00 | $2,000.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.85 | 0.05 | $16,000.00 | $800.00 |
7 | OFFICE FACILITIES | 24.00 | MTH |
18.00
| 17.00 | 1.00 | $500.00 | $500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.90
| 0.85 | 0.05 | $30,000.00 | $1,500.00 |
20 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 88,314.00 | SY |
88,164.00
| 62,340.00 | 25,824.00 | $4.90 | $126,537.60 |
22 | PORTLAND CEMENT FOR CSPB | 4,598.00 | TON |
3,135.29
| 2,860.71 | 274.58 | $152.00 | $41,736.16 |
23 | PRIME/TACK COAT FOR CSPB | 32,009.00 | GAL |
24,835.25
| 17,210.00 | 7,625.25 | $0.45 | $3,431.36 |
24 | COLD MILL AC PAVEMENT (0 - 1-1/2") | 54,495.00 | SF |
52,385.00
| 0.00 | 52,385.00 | $0.32 | $16,763.20 |
25 | AC PAVEMENT | 22,669.00 | TON |
22,128.15
| 15,292.59 | 6,835.56 | $70.00 | $478,489.20 |
59 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.85 | 0.05 | $370,000.00 | $18,500.00 |
|