Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.15
| 0.00 | 0.15 | $15,000.00 | $2,250.00 |
5 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.15
| 0.00 | 0.15 | $35,000.00 | $5,250.00 |
7 | OFFICE FACILITIES | 7.00 | MTH |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |