Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
5.00
| 4.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.80
| 0.65 | 0.15 | $15,000.00 | $2,250.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.70
| 0.60 | 0.10 | $35,000.00 | $3,500.00 |
7 | OFFICE FACILITIES | 7.00 | MTH |
5.00
| 4.00 | 1.00 | $5,000.00 | $5,000.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.45
| 0.30 | 0.15 | $150,000.00 | $22,500.00 |
12 | CONCRETE REMOVAL (NON-REINFORCED) | 919.00 | CY |
739.95
| 477.30 | 262.65 | $195.00 | $51,216.75 |
13 | UNCLASSIFIED EXCAVATION | 2,587.00 | CY |
1,160.35
| 801.05 | 359.30 | $195.00 | $70,063.50 |
15 | CRUSHED MISCELLANEOUS BASE | 2,077.00 | CY |
838.11
| 510.81 | 327.30 | $84.00 | $27,493.20 |
21 | AC PAVEMENT(PATCH BACK) | 370.00 | TON |
213.79
| 147.72 | 66.07 | $220.00 | $14,535.40 |
32 | PCC CURB, TYPE A1-VAR | 35.00 | LF |
20.00
| 0.00 | 20.00 | $37.00 | $740.00 |
33 | PCC CURB & GUTTER, TYPE A2-8 | 2,794.00 | LF |
2,794.00
| 2,084.00 | 710.00 | $45.00 | $31,950.00 |
34 | PCC WALK & DRIVEWAYS, 4" THICK | 17,616.00 | SF |
12,472.00
| 8,326.00 | 4,146.00 | $6.75 | $27,985.50 |
35 | PCC CURB RAMPS | 143.00 | CY |
115.43
| 94.95 | 20.48 | $775.00 | $15,872.00 |
36 | DETECTABLE WARNING SURFACE | 627.00 | SF |
510.00
| 435.00 | 75.00 | $42.00 | $3,150.00 |
37 | CROSS GUTTER | 458.00 | CY |
368.79
| 227.66 | 141.13 | $400.00 | $56,452.00 |
39 | TRAFFIC CONTROL | 1.00 | LS |
0.45
| 0.30 | 0.15 | $42,000.00 | $6,300.00 |
S-4A | TREE AND STUMP REMOVAL | | LS |
1.00
| 0.00 | 1.00 | $7,236.00 | $7,236.00 |
|